Class 8 | MATHS |
Chapter | TIME AND WORK, PIPES AND CISTERNS |
PEARSON IIT JEE FOUNDATION | Example |
Number Of Questions | 20 |
Academic Year | 2023-24 |
If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?
A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
A and B working together can do a piece of work in 12 days, B and C can do it in 15 days nd C and A can do the same work in 20 days b. How long would each of them take to complete the job?
To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
4 men or 5 women can construct a wall in 82 days. How long will it take for 5 men and 4 women to do the same ?
If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the
same work in 6 days, how long will 6 men and 24 boys take to complete the same work?
If X works 3 times as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they can complete the work working together.
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
One man and 3 days can together complete a piece of work in 10 days. One women alone can complete it in 30 days. How many women should accompany 3 men and 9 boys to complete the same work in 2 days ?
P,Q and R started a piece of work. They worked on it for 5 days, which P left
A,B and C can do a piece of work in 4 days, 5 days and 7 days respectively. They get ₹ 415 for completing the job. If A, B and C have worked together to complete the job, what is A's share?
Two men P and Q can complete a job in 6 days and 8 days respectively. The total remuneration for the job is ₹ 600. If they completed the job with the help of a woman in 3 days, find the shares of P,Q and the women respectively.
Two pipes A and B can fill a tank in 12 minutes and 18 minutes respectively. If both the pipes are opened simultaneously, how long will they take to fill the tank ?
Pipe A can fill a tank in 12 minutes,pipe B in 18 minutes and pipe C can empty the full tank in 36 minutes. If all of them are opend simultaneously, find the time taken to fill the empty tank.
Two taps P and Q can fill an empty tank in 15 hours and 30 hours respectively. Both taps were opened at 4 a.m. and after some time, tap Q was closed. It was found that the tank was full at 4 p.m. At what time was the tap Q shut ?
Three pipes X, Y and Z are fitted to a tank. For any pipe, the rate of filling is the same as that of the rate of empting. The rates of filiing of X, Y and Z are in the ratio `2:3:4`. X alone can fill the tank in 5 hours. Find the time taken in hours, to fill the tank if X is used as an emptying pipe while the other two are used as filling pipes.
Example questions and complete solutions for chapter TIME AND WORK PIPES AND CISTERNS of PEARSON IIT JEE FOUNDATION of Class 8