If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day then
To solve the problem, we need to derive a formula based on the information provided about the work done by different numbers of men over a specified number of days and hours.
1. Understanding the Work Formula:
The work done (W) can be expressed in terms of the number of men (M), the number of days (D), and the number of hours worked per day (H). The formula can be represented as:
W=M×D×H
2. Setting Up the First Scenario:
For the first scenario, we have:
- M1 men can do W1 work in D1 days working H1 hours per day.
Therefore, we can write:
W1=M1×D1×H1
3. Setting Up the Second Scenario:
For the second scenario, we have:
- M2 men can do W2 work in D2 days working H2 hours per day.
Thus, we can express this as:
W2=M2×D2×H2
4. Relating the Two Scenarios:
If we want to find out how many men are needed to complete a different piece of work, we can relate the two scenarios. If W2 is twice W1 (i.e., W2=2W1), we can substitute W1 from the first scenario into the second:
W2=2(M1×D1×H1)
5. Finding the Required Number of Men:
Now, we can set the equation for W2:
M2×D2×H2=2(M1×D1×H1)
Rearranging this gives:
M2=2(M1×D1×H1)D2×H2
6. Substituting Known Values:
If we have specific values for M1,D1,H1,D2, and H2, we can substitute them into the equation to find M2.
Example:
Let's say:
- M1=24
- D1=4
- H1=10
- D2=48
- H2=8
Substituting these values into the equation:
M2=2(24×4×10)48×8
Calculating M2:
1. Calculate 24×4×10=960
2. Calculate 48×8=384
3. Substitute into the equation:
M2=2×960384=1920384=5
Thus, 5 men are needed to complete the second piece of work.
The work done (W) can be expressed in terms of the number of men (M), the number of days (D), and the number of hours worked per day (H). The formula can be represented as:
W=M×D×H
For the first scenario, we have:
- M1 men can do W1 work in D1 days working H1 hours per day.
Therefore, we can write:
W1=M1×D1×H1
For the second scenario, we have:
- M2 men can do W2 work in D2 days working H2 hours per day.
Thus, we can express this as:
W2=M2×D2×H2
If we want to find out how many men are needed to complete a different piece of work, we can relate the two scenarios. If W2 is twice W1 (i.e., W2=2W1), we can substitute W1 from the first scenario into the second:
W2=2(M1×D1×H1)
Now, we can set the equation for W2:
M2×D2×H2=2(M1×D1×H1)
Rearranging this gives:
M2=2(M1×D1×H1)D2×H2
If we have specific values for M1,D1,H1,D2, and H2, we can substitute them into the equation to find M2.
Let's say:
- M1=24
- D1=4
- H1=10
- D2=48
- H2=8
M2=2(24×4×10)48×8
1. Calculate 24×4×10=960
2. Calculate 48×8=384
3. Substitute into the equation:
M2=2×960384=1920384=5
Similar Questions
50 persons can do a work in 12 days, working 6 h per day. 60 persons can do the same work in 8 days, working x h per days.The value of x is
View SolutionWorking 8 hours a day, 12 men can do a work in 30 days. Working 4 hours a day, 18 men can do the work in 30 days b. 40 days c. 45 days d. 50 days
View Solution
Knowledge Check
A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
A4B5411C6411D4411A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
A4B5411C6411D4411A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
A5511B4511C6411D6511
18 men can construct 200 m long wall in 16 days working 9 hours per day. In how many days can 36men construct 500 m long wall working 6 hours per day?
View SolutionA can finish a work in 10 days if he works 4 hours per day. B can complete it in 15 days if he works 5 hours per day. If they work 10 hours per day, then in how many days the work will be finished?
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 men
View SolutionIf 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
View SolutionIf x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
View Solution