If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day then

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to derive a formula based on the information provided about the work done by different numbers of men over a specified number of days and hours.

1. Understanding the Work Formula:
The work done (W) can be expressed in terms of the number of men (M), the number of days (D), and the number of hours worked per day (H). The formula can be represented as:
W=M×D×H

2. Setting Up the First Scenario:
For the first scenario, we have:
- M1 men can do W1 work in D1 days working H1 hours per day.
Therefore, we can write:
W1=M1×D1×H1

3. Setting Up the Second Scenario:
For the second scenario, we have:
- M2 men can do W2 work in D2 days working H2 hours per day.
Thus, we can express this as:
W2=M2×D2×H2

4. Relating the Two Scenarios:
If we want to find out how many men are needed to complete a different piece of work, we can relate the two scenarios. If W2 is twice W1 (i.e., W2=2W1), we can substitute W1 from the first scenario into the second:
W2=2(M1×D1×H1)

5. Finding the Required Number of Men:
Now, we can set the equation for W2:
M2×D2×H2=2(M1×D1×H1)
Rearranging this gives:
M2=2(M1×D1×H1)D2×H2

6. Substituting Known Values:
If we have specific values for M1,D1,H1,D2, and H2, we can substitute them into the equation to find M2.

Example:
Let's say:
- M1=24
- D1=4
- H1=10
- D2=48
- H2=8

Substituting these values into the equation:
M2=2(24×4×10)48×8

Calculating M2:
1. Calculate 24×4×10=960
2. Calculate 48×8=384
3. Substitute into the equation:
M2=2×960384=1920384=5

Thus, 5 men are needed to complete the second piece of work.

Updated on:7/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411
  • A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411
  • A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.

    A5511
    B4511
    C6411
    D6511