Working 8 hours a day, 12 men can do a work in 30 days. Working 4 hours a day, 18 men can do the work in 30 days b. 40 days c. 45 days d. 50 days
To solve the problem step by step, we need to determine how many days it would take for 18 men working 4 hours a day to complete the same work that 12 men can do in 30 days while working 8 hours a day.
Step 1: Calculate the total work done in man-hours
First, we calculate the total amount of work done in man-hours when 12 men work for 30 days at 8 hours a day.
Total work = Number of men × Number of hours per day × Number of days
Total Work=12 men×8 hours/day×30 days
Total Work=12×8×30=2880 man-hours
Step 2: Set up the equation for the second scenario
Now, we need to find out how many days (let's call it x) it will take for 18 men working 4 hours a day to complete the same amount of work (2880 man-hours).
Total work = Number of men × Number of hours per day × Number of days
2880=18 men×4 hours/day×x days
Step 3: Rearranging the equation to solve for x
Now we can rearrange the equation to solve for x:
x=288018×4
Step 4: Calculate x
Now let's calculate x:
x=288072
x=40
Conclusion
Thus, it will take 40 days for 18 men working 4 hours a day to complete the work.
Answer
The correct answer is b. 40 days.
---
First, we calculate the total amount of work done in man-hours when 12 men work for 30 days at 8 hours a day.
Total Work=12 men×8 hours/day×30 days
Total Work=12×8×30=2880 man-hours
Now, we need to find out how many days (let's call it x) it will take for 18 men working 4 hours a day to complete the same amount of work (2880 man-hours).
2880=18 men×4 hours/day×x days
Now we can rearrange the equation to solve for x:
x=288018×4
Now let's calculate x:
x=288072
x=40
Thus, it will take 40 days for 18 men working 4 hours a day to complete the work.
The correct answer is b. 40 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
If 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 menA60 menB20 menC50 menD40 men - Question 2 - Select One
If x men can do a piece of work in y days, in how many days will x men do the same work ?
AxzyBxyzCyzxDxyz - Question 3 - Select One
10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
AA)40 daysBB)60 daysCC)50 daysDD)30 days
12 men or 18 woman can do a work in 16 days. In how many days 12 men and 18 woman can do the work?
View SolutionA can do a piece of work in 15 days, which B can do in 10 days. B worked at it for 8 days. A can finish the remaining work in 2 days b. 3 days c. 5 days d. 10 days
View SolutionIf M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day then
View SolutionWorking 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View Solution