Doubtnut Promotions Sticky

150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.

Video Solution
Text Solution
Verified by Experts

The correct Answer is:N/a


Let the work is completed in 'n' days.
No. of workers engaged on second day =150-4=146
No. of workers engaged of third day =1502×4=142
Series formed from n terms : 150, 146, 142,….
Hera a=150,d=146150=142146=4
Sn=n2[2a+(n1)d]
=n2[2×150+(n1)(4)]=152n2n2
If 150 workers engaged then work completes in (n-8) days
150(n8)=1522n2
2n22n1200=0
n2n600=0
(n25)(n+24)=0
n25=0orn+24=0
n=25or n=24
n=24 is not possible.
Therefore, work is completed in 25 days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • Question 2 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 3 - Select One

    30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :

    A12
    B10
    C6
    Dnone of these