Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the task if she worked alone? Assume that Sudha is more efficient than Asha.
a. 25 days
b. 30 days
c. 60 days
d. 65 days
To solve the problem, we need to find out how long Asha will take to complete the task if she works alone. We are given two main pieces of information:
1. Working together, Asha and Sudha can complete the task in 20 days.
2. If Asha completes half the work and then Sudha completes the other half, the total time taken is 45 days.
Let's denote:
- Asha's time to complete the task alone as x days.
- Sudha's time to complete the task alone as y days.
Step 1: Set up the equations
From the first piece of information, we know that:
1x+1y=120
This equation represents the combined work rate of Asha and Sudha.
From the second piece of information, if Asha does half the work and then Sudha does the other half, we can write:
12⋅1x+12⋅1y=145
This simplifies to:
1x+1y=245
Step 2: Solve the equations
Now we have two equations:
1. 1x+1y=120 (Equation 1)
2. 1x+1y=245 (Equation 2)
From Equation 1, we can express 1y in terms of 1x:
1y=120−1x
Substituting this into Equation 2 gives us:
1x+(120−1x)=245
This simplifies to:
120=245
Step 3: Find a common value for x and y
Now, we can express x+y using the first equation:
x+y=90(from the half work equation)
Using the relationship x+y=90 in the second equation:
xy=90⋅20=1800
Step 4: Solve for x and y
We can now solve for x and y using the equations:
1. x+y=90
2. xy=1800
Using the quadratic formula:
Let x and y be the roots of the equation:
t2−(x+y)t+xy=0
Substituting the values:
t2−90t+1800=0
Using the quadratic formula:
t=90±√902−4⋅18002
t=90±√8100−72002
t=90±√9002
t=90±302
Calculating the two possible values:
1. t=1202=60
2. t=602=30
Thus, we have x=60 and y=30.
Conclusion
Since Asha takes x days to complete the task alone, the answer is:
Asha will take 60 days to complete the task alone.
Final Answer
c. 60 days
2. If Asha completes half the work and then Sudha completes the other half, the total time taken is 45 days.
- Asha's time to complete the task alone as x days.
- Sudha's time to complete the task alone as y days.
1x+1y=120
This equation represents the combined work rate of Asha and Sudha.
12⋅1x+12⋅1y=145
This simplifies to:
1x+1y=245
1. 1x+1y=120 (Equation 1)
2. 1x+1y=245 (Equation 2)
1y=120−1x
1x+(120−1x)=245
This simplifies to:
120=245
x+y=90(from the half work equation)
xy=90⋅20=1800
1. x+y=90
2. xy=1800
Let x and y be the roots of the equation:
t2−(x+y)t+xy=0
Substituting the values:
t2−90t+1800=0
t=90±√902−4⋅18002
t=90±√8100−72002
t=90±√9002
t=90±302
1. t=1202=60
2. t=602=30
Asha will take 60 days to complete the task alone.
c. 60 days
Topper's Solved these Questions
Similar Questions
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the task if she worked alone? Assume that Sudha is more efficient than Asha.
a. 25 days
b. 30 days
c. 60 days
d. 65 days
View SolutionA alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View Solution
Knowledge Check
A man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone ?
A72 daysB73 daysC49 daysD62 daysA alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
A18 daysB24 daysC16 daysD20 daysA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32
A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View SolutionVirat can complete a task a 20 days, whereas Anu can complete the same task in 15 days. How long will it take for Virat and Anu to complete the task if they worked together
View SolutionA man and a boy can complete a work together in 24 days. If for the last six days man alone does the work then it is completed in 26 days. How long the boy will take to complete the work alone?
View SolutionA and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View Solution