A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in a 1413days b. 1523days c. 1613days d. 1823days
To solve the problem, we need to determine how many days A and B will take to complete the work when they work alternately. Here’s the step-by-step solution:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days, so the work done by A in one day is:
Work done by A in one day=112
- B can complete the work in 18 days, so the work done by B in one day is:
Work done by B in one day=118
Step 2: Calculate the work done in 2 days (one cycle of A and B).
- In the first day, A works, and in the second day, B works. Therefore, the total work done in 2 days is:
Total work in 2 days=Work done by A+Work done by B=112+118
Step 3: Find a common denominator and add the fractions.
- The least common multiple (LCM) of 12 and 18 is 36. So we convert the fractions:
112=336and118=236
- Therefore,
Total work in 2 days=336+236=536
Step 4: Determine how many cycles are needed to complete the work.
- Let’s assume the total work is 1 unit. To find out how many cycles (2 days) are needed to complete 1 unit of work:
Number of cycles=1 unit536=365=7.2 cycles
- Since each cycle takes 2 days, the total days for 7 complete cycles is:
7 cycles×2 days/cycle=14 days
Step 5: Calculate the remaining work after 14 days.
- After 14 days, the work done is:
7 cycles×536=3536
- The remaining work is:
1−3536=136
Step 6: Determine how long it takes to complete the remaining work.
- On the 15th day, A will work again. The work done by A in one day is:
Work done by A in one day=112
- To complete 136 of the work, we need to find out how much time it will take:
Time to complete 136=136112=136×12=13 days
Step 7: Calculate the total time taken to complete the work.
- The total time taken is:
14 days+13 days=1413 days
Final Answer:
The total time taken to complete the work is:
1413 days
- A can complete the work in 12 days, so the work done by A in one day is:
Work done by A in one day=112
- B can complete the work in 18 days, so the work done by B in one day is:
Work done by B in one day=118
- In the first day, A works, and in the second day, B works. Therefore, the total work done in 2 days is:
Total work in 2 days=Work done by A+Work done by B=112+118
- The least common multiple (LCM) of 12 and 18 is 36. So we convert the fractions:
112=336and118=236
- Therefore,
Total work in 2 days=336+236=536
- Let’s assume the total work is 1 unit. To find out how many cycles (2 days) are needed to complete 1 unit of work:
Number of cycles=1 unit536=365=7.2 cycles
- Since each cycle takes 2 days, the total days for 7 complete cycles is:
7 cycles×2 days/cycle=14 days
- After 14 days, the work done is:
7 cycles×536=3536
- The remaining work is:
1−3536=136
- On the 15th day, A will work again. The work done by A in one day is:
Work done by A in one day=112
- To complete 136 of the work, we need to find out how much time it will take:
Time to complete 136=136112=136×12=13 days
- The total time taken is:
14 days+13 days=1413 days
The total time taken to complete the work is:
1413 days
Topper's Solved these Questions
Similar Questions
A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in a 1413days b. 1523days c. 1613days d. 1823days
View SolutionA and B can complete a work in 18 days and 15 days respectively. They started doing the work together but after 3 days A had to leave and B alone completed the remaining work. The whole work was completed in 934days b. 1014 days c. 1212days d. 1234days
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a work in 12 days and 18 days, respectively. A begins to do the work and they work alternately one at a time for 1 day each. The whole work will be completed in how many days?
A1423B1413C1425D1457 - Question 2 - Select One
X and Y can do a piece of work in 4 days and 6 days resepectively. If Y works on the first day and they work on alternate days, in how many days will twice the amount of work be complete?
A923B1023C915D912 - Question 3 - Select One
A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, A beginning, in how many days, he work will be completed?
A1012daysB1014 daysC1023 daysD1013 days
A and B can do a piece of work in 6 days and 4 days respectively. A started the work, worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.
View SolutionA and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionA, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
View SolutionChandni and Divakar can do a piece of work in 9 days and 12 days respectively. If they work for a day alternatively, Chandni beginning, in how many days, the work will be completed?
View SolutionA and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in
View Solution