Doubtnut Promotions Sticky

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in a 1413days b. 1523days c. 1613days d. 1823days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine how many days A and B will take to complete the work when they work alternately. Here’s the step-by-step solution:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days, so the work done by A in one day is:
Work done by A in one day=112

- B can complete the work in 18 days, so the work done by B in one day is:
Work done by B in one day=118

Step 2: Calculate the work done in 2 days (one cycle of A and B).
- In the first day, A works, and in the second day, B works. Therefore, the total work done in 2 days is:
Total work in 2 days=Work done by A+Work done by B=112+118

Step 3: Find a common denominator and add the fractions.
- The least common multiple (LCM) of 12 and 18 is 36. So we convert the fractions:
112=336and118=236
- Therefore,
Total work in 2 days=336+236=536

Step 4: Determine how many cycles are needed to complete the work.
- Let’s assume the total work is 1 unit. To find out how many cycles (2 days) are needed to complete 1 unit of work:
Number of cycles=1 unit536=365=7.2 cycles
- Since each cycle takes 2 days, the total days for 7 complete cycles is:
7 cycles×2 days/cycle=14 days

Step 5: Calculate the remaining work after 14 days.
- After 14 days, the work done is:
7 cycles×536=3536
- The remaining work is:
13536=136

Step 6: Determine how long it takes to complete the remaining work.
- On the 15th day, A will work again. The work done by A in one day is:
Work done by A in one day=112
- To complete 136 of the work, we need to find out how much time it will take:
Time to complete 136=136112=136×12=13 days

Step 7: Calculate the total time taken to complete the work.
- The total time taken is:
14 days+13 days=1413 days

Final Answer:
The total time taken to complete the work is:
1413 days

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a work in 12 days and 18 days, respectively. A begins to do the work and they work alternately one at a time for 1 day each. The whole work will be completed in how many days?

    A1423
    B1413
    C1425
    D1457
  • Question 2 - Select One

    X and Y can do a piece of work in 4 days and 6 days resepectively. If Y works on the first day and they work on alternate days, in how many days will twice the amount of work be complete?

    A923
    B1023
    C915
    D912
  • Question 3 - Select One

    A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, A beginning, in how many days, he work will be completed?

    A1012days
    B1014 days
    C1023 days
    D1013 days