Doubtnut Promotions Sticky

A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of the work. In how many days will the work be completed ? 15 days b. 22 days c. 25  days d. 35 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow the process outlined in the video transcript.

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 24 days, so A's work in one day = 124.
- B can complete the work in 36 days, so B's work in one day = 136.
- C can complete the work in 48 days, so C's work in one day = 148.

Step 2: Calculate the combined work done by A, B, and C in one day.
Work done by A, B, and C in one day=124+136+148
To add these fractions, we need a common denominator. The least common multiple (LCM) of 24, 36, and 48 is 144.

Converting each fraction:
- 124=6144
- 136=4144
- 148=3144

Now, adding them together:
6144+4144+3144=13144

Step 3: Calculate the work done in the first 4 days.
In 4 days, A, B, and C will complete:
Work done in 4 days=4×13144=52144=1336

Step 4: Calculate the remaining work after 4 days.
The total work is considered as 1 (or 1 whole unit). Therefore, the remaining work is:
Remaining work=11336=361336=2336

Step 5: Determine how much work is done by B alone in the last 3 days.
Since A leaves 3 days before the work is completed, only B works for the last 3 days. B's work in one day is 136, so in 3 days, B will complete:
Work done by B in 3 days=3×136=336=112

Step 6: Calculate the remaining work after B's contribution.
After B works for 3 days, the remaining work is:
Remaining work=2336112
To subtract these fractions, we convert 112 to have a common denominator of 36:
112=336
Thus,
Remaining work=2336336=2036=59

Step 7: Calculate the work done by A and B together.
A and B together can complete:
A's work+B's work=124+136
Finding a common denominator (which is 72):
- 124=372
- 136=272

Thus,
Work done by A and B together=372+272=572

Step 8: Calculate the time taken by A and B to complete the remaining work.
To find the time taken to complete 59 work at a rate of 572:
Time=Remaining workWork done per day=5/95/72=59×725=729=8 days

Step 9: Calculate the total time taken to complete the work.
The total time taken is:
Total time=Time with A, B, and C+Time with B+Time with A and B
=4+3+8=15 days

Final Answer
The work will be completed in 15 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?

    A20 days
    B18 days
    C16 days
    D15 days
  • Question 2 - Select One

    A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • Question 3 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these