Doubtnut Promotions Sticky

A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.

A

6 days

B

7 days

C

9 days

D

8 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we will follow these steps:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 16 days, so B's work rate is 116 of the work per day.

Step 2: Find the combined work rate of A and B.
- To find the combined work rate, we need to find a common denominator. The LCM of 12 and 16 is 48.
- A's work in 48 hours: 4812=4 units of work.
- B's work in 48 hours: 4816=3 units of work.
- Therefore, together they can do 4+3=7 units of work in one day.

Step 3: Determine the total work to be done.
- The total work is equivalent to 48 units (as calculated from the LCM).

Step 4: Calculate the time taken if A leaves 2 days before the work is finished.
- Let the total number of days taken to finish the work be x.
- Since A leaves 2 days before the work is finished, A works for x2 days, while B works for the entire x days.

Step 5: Set up the equation for total work done.
- Work done by A in x2 days: 4(x2)
- Work done by B in x days: 3x
- Total work equation:
4(x2)+3x=48

Step 6: Solve the equation.
1. Expand the equation:
4x8+3x=48
2. Combine like terms:
7x8=48
3. Add 8 to both sides:
7x=56
4. Divide by 7:
x=8

Conclusion:
- The total number of days taken to finish the work is 8 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

    A6
    B5
    C7
    D7.2
  • Question 2 - Select One

    A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?

    A4.33
    B4.5
    C4.66
    DNone
  • Question 3 - Select One

    A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

    A10
    B8
    C12
    D9