Doubtnut Promotions Sticky

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:20


To solve the problem step by step, we will first determine the work done by A, B, and C, and then set up an equation based on the information given in the question.

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 20 days, so A's work in one day = 1/20 of the work.
- B can complete the work in 45 days, so B's work in one day = 1/45 of the work.
- C can complete the work in 120 days, so C's work in one day = 1/120 of the work.

Step 2: Find the Least Common Multiple (LCM) of the days.
The LCM of 20, 45, and 120 is 360. This means the total work can be considered as 360 units.

Step 3: Calculate the efficiency (work done in one day) of A, B, and C.
- A's efficiency = 360 / 20 = 18 units/day.
- B's efficiency = 360 / 45 = 8 units/day.
- C's efficiency = 360 / 120 = 3 units/day.

Step 4: Set up the equation based on the work done.
Let X be the total number of days taken to complete the work.

- A worked for X10 days (since A left 10 days before completion).
- B worked for X5 days (since B left 5 days before completion).
- C worked for X days.

Step 5: Write the equation for the total work done.
The total work done by A, B, and C can be expressed as:
18(X10)+8(X5)+3X=360

Step 6: Expand and simplify the equation.
Expanding the equation:
18X180+8X40+3X=360

Combine like terms:
(18X+8X+3X)220=360
29X220=360

Step 7: Solve for X.
Add 220 to both sides:
29X=580

Now, divide by 29:
X=58029
X=20

Conclusion:
The total work is completed in 20 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • Question 2 - Select One

    A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • Question 3 - Select One

    A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

    A7
    B10
    C12
    D9