Doubtnut Promotions Sticky

A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

A

7

B

10

C

12

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find out how many days the work was completed when A, B, and C worked together, with B leaving 3 days before the work was finished.

Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.

Step 2: Calculate the combined work rate of A, B, and C.
The combined work rate of A, B, and C is:
Combined work rate=120+124+130

To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 20, 24, and 30 is 120.

Now, convert each fraction:
- 120=6120
- 124=5120
- 130=4120

Adding these together:
Combined work rate=6120+5120+4120=15120=18

So, A, B, and C together can complete 18 of the work in one day.

Step 3: Let the total number of days to complete the work be x.
Since B left 3 days before the work was completed, B worked for x3 days, while A and C worked for the entire x days.

Step 4: Set up the equation based on the work done.
The work done by A, B, and C can be expressed as:
Work done by A in x days=As rate×x=x20
Work done by B in (x3) days=Bs rate×(x3)=x324
Work done by C in x days=Cs rate×x=x30

The total work done by A, B, and C together must equal 1 (the whole work):
x20+x324+x30=1

Step 5: Solve the equation.
To solve this equation, we first find a common denominator for the fractions, which is 120:
6x120+5(x3)120+4x120=1

Combine the fractions:
6x+5(x3)+4x120=1
6x+5x15+4x=120
15x15=120
15x=135
x=9

Step 6: Conclusion
The total number of days taken to complete the work is 9 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

    A660/47
    B640/47
    C680/47
    D665/47
  • Question 2 - Select One

    A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A13
    B12
    C14
    D11
  • Question 3 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10