A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
7
10
12
9
To solve the problem, we need to find out how many days the work was completed when A, B, and C worked together, with B leaving 3 days before the work was finished.
Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
Step 2: Calculate the combined work rate of A, B, and C.
The combined work rate of A, B, and C is:
Combined work rate=120+124+130
To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 20, 24, and 30 is 120.
Now, convert each fraction:
- 120=6120
- 124=5120
- 130=4120
Adding these together:
Combined work rate=6120+5120+4120=15120=18
So, A, B, and C together can complete 18 of the work in one day.
Step 3: Let the total number of days to complete the work be x.
Since B left 3 days before the work was completed, B worked for x−3 days, while A and C worked for the entire x days.
Step 4: Set up the equation based on the work done.
The work done by A, B, and C can be expressed as:
Work done by A in x days=A′s rate×x=x20
Work done by B in (x−3) days=B′s rate×(x−3)=x−324
Work done by C in x days=C′s rate×x=x30
The total work done by A, B, and C together must equal 1 (the whole work):
x20+x−324+x30=1
Step 5: Solve the equation.
To solve this equation, we first find a common denominator for the fractions, which is 120:
6x120+5(x−3)120+4x120=1
Combine the fractions:
6x+5(x−3)+4x120=1
6x+5x−15+4x=120
15x−15=120
15x=135
x=9
Step 6: Conclusion
The total number of days taken to complete the work is 9 days.
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
The combined work rate of A, B, and C is:
Combined work rate=120+124+130
- 120=6120
- 124=5120
- 130=4120
Combined work rate=6120+5120+4120=15120=18
Since B left 3 days before the work was completed, B worked for x−3 days, while A and C worked for the entire x days.
The work done by A, B, and C can be expressed as:
Work done by A in x days=A′s rate×x=x20
Work done by B in (x−3) days=B′s rate×(x−3)=x−324
Work done by C in x days=C′s rate×x=x30
x20+x−324+x30=1
To solve this equation, we first find a common denominator for the fractions, which is 120:
6x120+5(x−3)120+4x120=1
6x+5(x−3)+4x120=1
6x+5x−15+4x=120
15x−15=120
15x=135
x=9
The total number of days taken to complete the work is 9 days.
Similar Questions
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
- Question 1 - Select One
X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?
A660/47B640/47C680/47D665/47 - Question 2 - Select One
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11 - Question 3 - Select One
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can do a piece of work in 12, 15 and 20 days respectively. In how many days will all three do this work together ?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View Solution