A group of workers promise to complete a piece of work in 10 days, but five of them do not report for work. If it took the remaining workers 12 days to complete the work, then the number of workers originally hired was 15 b. 25 c. 30 d. 45
Step by step video & image solution for A group of workers promise to complete a piece of work in 10 days, but five of them do not report for work. If it took the remaining workers 12 days to complete the work, then the number of workers originally hired was 15 b. 25 c. 30 d. 45 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
20 workers working for 5 hours a day complete a work in 10 days . If 25 workers are employed to work 10 hours a day, what is the time required to complete the work ?
View SolutionA can do a piece of work in 80 days. A works for 10 days, then B complete the remaining work in 42 days. In how many days will (A + B) do this work together
View Solution
Knowledge Check
- Question 1 - Select One
A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
A100B300C600D200 - Question 2 - Select One
A can complete a piece of work in 25 days. After working for 5 days, remaining work is completed in 15 days with the help of B. Then B can complete the whole work in how many days?
A75 daysB72 daysC60 daysD90 days - Question 3 - Select One
A, B and C can complete a piece of work in 10 days, 20 days and 25 days, respectively. If they tak 40 days to complete a piece of work, then in how many days can C alone complete the work ?
A65 daysB76 daysC95 daysD190 days
A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
View SolutionA work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
View Solution20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?
View Solution