12 men working 8 hours per day complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required is a. 4 b. 5 c. 6 d. 8
To solve the problem, we need to determine how many men are required to complete the same piece of work in 8 days, working 15 hours a day, given that 12 men can complete it in 10 days while working 8 hours a day.
1. Calculate the Total Work Done in Man-Hours:
- The total work can be calculated using the formula:
Total Work=Number of Men×Hours per Day×Number of Days
- For the initial scenario:
Total Work=12men×8hours/day×10days
- Calculate:
Total Work=12×8×10=960man-hours
2. Determine the New Working Conditions:
- Now, we need to find out how many men (let's denote this as x) are required to complete the same work in 8 days while working 15 hours a day.
3. Set Up the Equation for the New Scenario:
- The equation for the new scenario is:
Total Work=xmen×15hours/day×8days
- This can be written as:
960=x×15×8
4. Simplify the Equation:
- Simplify the right side:
960=x×120
5. Solve for x:
- Rearranging gives:
x=960120
- Calculate:
x=8
Conclusion:
The number of men required to complete the work in 8 days, working 15 hours a day, is 8 men. Therefore, the correct answer is d. 8.
- The total work can be calculated using the formula:
Total Work=Number of Men×Hours per Day×Number of Days
- For the initial scenario:
Total Work=12men×8hours/day×10days
- Calculate:
Total Work=12×8×10=960man-hours
- Now, we need to find out how many men (let's denote this as x) are required to complete the same work in 8 days while working 15 hours a day.
- The equation for the new scenario is:
Total Work=xmen×15hours/day×8days
- This can be written as:
960=x×15×8
- Simplify the right side:
960=x×120
- Rearranging gives:
x=960120
- Calculate:
x=8
The number of men required to complete the work in 8 days, working 15 hours a day, is 8 men. Therefore, the correct answer is d. 8.
Topper's Solved these Questions
Similar Questions
On working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution
Knowledge Check
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D328 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
A2012 daysB2035 daysC21daysD2047 daysIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
View SolutionIf 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
View Solution12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View SolutionWorking 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
View Solution