20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will use the concept of work done by men in a given time.

Step 1: Understand the given information
We know that:
- 20 men complete 13 of the work in 20 days.

Step 2: Calculate the total work
If 20 men complete 13 of the work in 20 days, then the total work W can be calculated as follows:
- Work done by 20 men in 20 days = 13W
- Therefore, total work W=3×(work done in 20 days)=3×(20 men×20 days)

Step 3: Calculate the total work
W=3×(20×20)=3×400=1200 man-days

Step 4: Determine the remaining work
Since 13 of the work is completed, the remaining work is:
Remaining work=W13W=23W=23×1200=800 man-days

Step 5: Calculate the number of men required to finish the remaining work
We need to finish the remaining work of 800 man-days in 25 days. Let x be the number of men required to complete this work:
x men×25 days=800 man-days

Step 6: Solve for x
x=80025=32 men

Step 7: Calculate how many more men are needed
Initially, there were 20 men working. Therefore, the additional number of men required is:
Additional men=3220=12

Final Answer
The number of additional men required to finish the rest of the work in 25 more days is 12.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?

    A12
    B20
    C18
    D24
  • 20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?

    A10
    B12
    C15
    D20
  • 20 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?

    A20
    B12
    C18
    D40