20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? b. c. d.
To solve the problem step by step, we will use the concept of work done by men in a given time.
Step 1: Understand the given information
We know that:
- 20 men complete 13 of the work in 20 days.
Step 2: Calculate the total work
If 20 men complete 13 of the work in 20 days, then the total work W can be calculated as follows:
- Work done by 20 men in 20 days = 13W
- Therefore, total work W=3×(work done in 20 days)=3×(20 men×20 days)
Step 3: Calculate the total work
W=3×(20×20)=3×400=1200 man-days
Step 4: Determine the remaining work
Since 13 of the work is completed, the remaining work is:
Remaining work=W−13W=23W=23×1200=800 man-days
Step 5: Calculate the number of men required to finish the remaining work
We need to finish the remaining work of 800 man-days in 25 days. Let x be the number of men required to complete this work:
x men×25 days=800 man-days
Step 6: Solve for x
x=80025=32 men
Step 7: Calculate how many more men are needed
Initially, there were 20 men working. Therefore, the additional number of men required is:
Additional men=32−20=12
Final Answer
The number of additional men required to finish the rest of the work in 25 more days is 12.
---
We know that:
- 20 men complete 13 of the work in 20 days.
If 20 men complete 13 of the work in 20 days, then the total work W can be calculated as follows:
- Work done by 20 men in 20 days = 13W
- Therefore, total work W=3×(work done in 20 days)=3×(20 men×20 days)
W=3×(20×20)=3×400=1200 man-days
Since 13 of the work is completed, the remaining work is:
Remaining work=W−13W=23W=23×1200=800 man-days
We need to finish the remaining work of 800 man-days in 25 days. Let x be the number of men required to complete this work:
x men×25 days=800 man-days
x=80025=32 men
Initially, there were 20 men working. Therefore, the additional number of men required is:
Additional men=32−20=12
The number of additional men required to finish the rest of the work in 25 more days is 12.
Topper's Solved these Questions
Similar Questions
Knowledge Check
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D2420 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
A10B12C15D2020 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?
A20B12C18D40
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution12 men can complete one third of the work in 8 days. In how many days can 16 men complete that work?
View Solution20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
View SolutionTwenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View SolutionTwenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution