Doubtnut Promotions Sticky

A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. 1 b.  114 c. 134 d. 112

Video Solution
|
Answer

Step by step video & image solution for A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. 1 b. \ 1 1/4 c. 1 3/4 d. 1 1/2 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 300 men can do a piece of work in 16 days. How many men would do (1/5) of the work in 15 days ?

    A56
    B64
    C60
    D72
  • Question 2 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 3 - Select One

    A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?

    A50
    B40
    C56
    D58