Doubtnut Promotions Sticky

A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8 days b. 12 days c. 9 days d. 10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Define the variables
Let x be the number of days planned to complete the job.

Step 2: Calculate the planned daily production
The total number of pieces to be completed is 360. Therefore, the planned number of pieces made per day is:
Planned daily production=360x

Step 3: Consider the increased production
According to the problem, if the team makes 4 more pieces per day than planned, they complete the job one day ahead of schedule. Hence, the new daily production becomes:
New daily production=360x+4

Step 4: Calculate the new time taken to complete the job
Since they finish a day early, the new time taken to complete the job is x1 days. Therefore, the total production in x1 days is:
Total production=(360x+4)(x1)

Step 5: Set up the equation
Since the total production must equal 360 pieces, we can set up the equation:
(360x+4)(x1)=360

Step 6: Expand the equation
Expanding the left-hand side gives:
360(x1)x+4(x1)=360
360360x+4x4=360

Step 7: Simplify the equation
Now we simplify:
360x+4x4=0
4x4=360x
Multiplying through by x to eliminate the fraction:
4x24x=360

Step 8: Rearrange into standard quadratic form
Rearranging gives:
4x24x360=0
Dividing the entire equation by 4 simplifies it:
x2x90=0

Step 9: Factor or use the quadratic formula
To solve for x, we can factor:
(x10)(x+9)=0
This gives us:
x10=0orx+9=0
Thus, x=10 or x=9. Since time cannot be negative, we have:
x=10

Conclusion
The team took 10 days to complete the job.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Shantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?

    A6 days
    B18 days
    C5 days
    D12 days