A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8 days b. 12 days c. 9 days d. 10 days
To solve the problem, we will follow these steps:
Step 1: Define the variables
Let x be the number of days planned to complete the job.
Step 2: Calculate the planned daily production
The total number of pieces to be completed is 360. Therefore, the planned number of pieces made per day is:
Planned daily production=360x
Step 3: Consider the increased production
According to the problem, if the team makes 4 more pieces per day than planned, they complete the job one day ahead of schedule. Hence, the new daily production becomes:
New daily production=360x+4
Step 4: Calculate the new time taken to complete the job
Since they finish a day early, the new time taken to complete the job is x−1 days. Therefore, the total production in x−1 days is:
Total production=(360x+4)(x−1)
Step 5: Set up the equation
Since the total production must equal 360 pieces, we can set up the equation:
(360x+4)(x−1)=360
Step 6: Expand the equation
Expanding the left-hand side gives:
360(x−1)x+4(x−1)=360
360−360x+4x−4=360
Step 7: Simplify the equation
Now we simplify:
−360x+4x−4=0
4x−4=360x
Multiplying through by x to eliminate the fraction:
4x2−4x=360
Step 8: Rearrange into standard quadratic form
Rearranging gives:
4x2−4x−360=0
Dividing the entire equation by 4 simplifies it:
x2−x−90=0
Step 9: Factor or use the quadratic formula
To solve for x, we can factor:
(x−10)(x+9)=0
This gives us:
x−10=0orx+9=0
Thus, x=10 or x=−9. Since time cannot be negative, we have:
x=10
Conclusion
The team took 10 days to complete the job.
---
Let x be the number of days planned to complete the job.
The total number of pieces to be completed is 360. Therefore, the planned number of pieces made per day is:
Planned daily production=360x
According to the problem, if the team makes 4 more pieces per day than planned, they complete the job one day ahead of schedule. Hence, the new daily production becomes:
New daily production=360x+4
Since they finish a day early, the new time taken to complete the job is x−1 days. Therefore, the total production in x−1 days is:
Total production=(360x+4)(x−1)
Since the total production must equal 360 pieces, we can set up the equation:
(360x+4)(x−1)=360
Expanding the left-hand side gives:
360(x−1)x+4(x−1)=360
360−360x+4x−4=360
Now we simplify:
−360x+4x−4=0
4x−4=360x
Multiplying through by x to eliminate the fraction:
4x2−4x=360
Rearranging gives:
4x2−4x−360=0
Dividing the entire equation by 4 simplifies it:
x2−x−90=0
To solve for x, we can factor:
(x−10)(x+9)=0
This gives us:
x−10=0orx+9=0
Thus, x=10 or x=−9. Since time cannot be negative, we have:
x=10
The team took 10 days to complete the job.
Topper's Solved these Questions
Similar Questions
Knowledge Check
Shantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?
A6 daysB18 daysC5 daysD12 days
12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work? 2 days b. 3 days c. 4 days d. 5days e. none of these
View SolutionA and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionX can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work ? 1313 days b. 15 days c. 20 days d. 56 days
View SolutionA and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
View Solution8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10days b. 12 days c. 14 days d. 16 days e. none of these
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View Solution