12 men and 18 boys, working , hours a day, can do a piece of work in 60 day. If a man works equal to 2 boys, then how many boys will be required to help 21 men to do twice the work in 50 day, working 9 hours a day? b. c. d.
To solve the problem, we will use the work formula:
W1M1×D1×T1=W2M2×D2×T2
Where:
- W1 is the first work done,
- M1 is the number of men working in the first scenario,
- D1 is the number of days they work,
- T1 is the time worked per day,
- W2 is the second work to be done,
- M2 is the number of men working in the second scenario,
- D2 is the number of days they work in the second scenario,
- T2 is the time worked per day in the second scenario.
Step 1: Calculate the total work done in the first scenario.
Given:
- 12 men and 18 boys working 7.5 hours a day for 60 days.
- Since 1 man works equivalent to 2 boys, we convert the men to boys:
- 12 men = 24 boys
- Total boys = 24 boys + 18 boys = 42 boys.
Now, we can calculate the total work done in terms of "boy-hours":
W1=42 boys×60 days×7.5 hours/day
Calculating:
W1=42×60×7.5=18900 boy-hours
Step 2: Determine the work needed for the second scenario.
In the second scenario, we need to do twice the work:
W2=2×W1=2×18900=37800 boy-hours
Step 3: Set up the equation for the second scenario.
We have:
- M2=21 men (which is equivalent to 21×2=42 boys),
- D2=50 days,
- T2=9 hours/day.
We need to find X, the number of boys required to help the 21 men:
W2=(M2+X)×D2×T2
37800=(21+X)×50×9
Step 4: Solve for X.
Calculating the right side:
37800=(21+X)×450
Now, divide both sides by 450:
37800450=21+X
84=21+X
Now, isolate X:
X=84−21=63
Step 5: Conclusion
Thus, the number of boys required to help 21 men to do twice the work in 50 days, working 9 hours a day is:
Answer: 63 boys
- W1 is the first work done,
- M1 is the number of men working in the first scenario,
- D1 is the number of days they work,
- T1 is the time worked per day,
- W2 is the second work to be done,
- M2 is the number of men working in the second scenario,
- D2 is the number of days they work in the second scenario,
- T2 is the time worked per day in the second scenario.
- 12 men and 18 boys working 7.5 hours a day for 60 days.
- Since 1 man works equivalent to 2 boys, we convert the men to boys:
- 12 men = 24 boys
- Total boys = 24 boys + 18 boys = 42 boys.
W1=42 boys×60 days×7.5 hours/day
W1=42×60×7.5=18900 boy-hours
W2=2×W1=2×18900=37800 boy-hours
- M2=21 men (which is equivalent to 21×2=42 boys),
- D2=50 days,
- T2=9 hours/day.
W2=(M2+X)×D2×T2
37800=(21+X)×50×9
37800=(21+X)×450
37800450=21+X
84=21+X
X=84−21=63
Answer: 63 boys
Topper's Solved these Questions
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
12 men and 18 boys working 712 hours a day can do a work in 60 days. If one man works equal to 2 boys, then the number of boys required to help 21 men to do twice the work in 50 days working 9 hours a day will be:
A42B44C46DNone of these - Question 2 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 3 - Select One
If x men can do a piece of work in y days, in how many days will x men do the same work ?
AxzyBxyzCyzxDxyz
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionTwelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
View Solution