A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed?
Video Solution
Text Solution
The correct Answer is:1
|
Answer
Step by step video, text & image solution for A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Related Playlists
Knowledge Check
- Question 1 - Select One
A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b. 114 c. 134 d. 112
A1 dayB1 1/4 daysC1 3/4 daysD1 1/2 days - Question 1 - Select One
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
A2B3C4D5 - Question 1 - Select One
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?
A2B3C4D5 - Question 1 - Select One
A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
A30B15C25D20 - Question 1 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 1 - Select One
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24 - Question 1 - Select One
A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
A20B25C30D32 - Question 1 - Select One
A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
A6B12C18D24
Similar Questions
A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. 1 b. 114 c. 134 d. 112
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution