Doubtnut Promotions Sticky

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:1

|
Answer

Step by step video, text & image solution for A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b.  114 c. 134 d. 112

    A1 day
    B1 1/4 days
    C1 3/4 days
    D1 1/2 days
  • Question 1 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 1 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 1 - Select One

    A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?

    A30
    B15
    C25
    D20
  • Question 1 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 1 - Select One

    40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?

    A12
    B20
    C18
    D24
  • Question 1 - Select One

    A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?

    A20
    B25
    C30
    D32
  • Question 1 - Select One

    A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :

    A6
    B12
    C18
    D24

Similar Questions