A job can be done by 3 skilled worksmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together? 8 days b. 10 days c. 12 days d. 11 days
To solve the problem of how many days it will take for 3 skilled worksmen and 5 boys to complete a job together, we can follow these steps:
Step 1: Determine the work done by the skilled worksmen in one day.
- If 3 skilled worksmen can complete the job in 20 days, then the work done by them in one day is:
Work done by 3 worksmen in 1 day=120 of the job
Step 2: Determine the work done by the boys in one day.
- If 5 boys can complete the job in 30 days, then the work done by them in one day is:
Work done by 5 boys in 1 day=130 of the job
Step 3: Combine the work done by both groups in one day.
- To find the total work done by both the skilled worksmen and the boys together in one day, we add their individual work rates:
Total work done in 1 day=120+130
Step 4: Find a common denominator and add the fractions.
- The least common multiple of 20 and 30 is 60. Thus, we convert the fractions:
120=360and130=260
- Now we can add them:
360+260=560
Step 5: Simplify the total work done in one day.
- Simplifying 560 gives:
560=112
- This means that together, they can complete 112 of the job in one day.
Step 6: Calculate the total time to complete the job.
- If they can complete 112 of the job in one day, then the total time to complete the job is:
Total days=1112=12 days
Final Answer:
Thus, if 3 skilled worksmen and 5 boys work together, they will complete the job in 12 days.
---
- If 3 skilled worksmen can complete the job in 20 days, then the work done by them in one day is:
Work done by 3 worksmen in 1 day=120 of the job
- If 5 boys can complete the job in 30 days, then the work done by them in one day is:
Work done by 5 boys in 1 day=130 of the job
- To find the total work done by both the skilled worksmen and the boys together in one day, we add their individual work rates:
Total work done in 1 day=120+130
- The least common multiple of 20 and 30 is 60. Thus, we convert the fractions:
120=360and130=260
- Now we can add them:
360+260=560
- Simplifying 560 gives:
560=112
- This means that together, they can complete 112 of the job in one day.
- If they can complete 112 of the job in one day, then the total time to complete the job is:
Total days=1112=12 days
Thus, if 3 skilled worksmen and 5 boys work together, they will complete the job in 12 days.
Topper's Solved these Questions
Similar Questions
3 men or 6 women can do a piece of work in 20 days. In how many days will 12 men and 8 women do the same work? 312days b. 334days c. 4 days d. 5 days
View SolutionA and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
View SolutionA and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone? a. 24 days b. 32 days c. 40 days d. 48 days
View Solution12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work? 2 days b. 3 days c. 4 days d. 5days e. none of these
View SolutionA and B can finish a work, working on alternate days, in 19 days, when A works on the first However, they can finish the work, working alternate days, in 1956 days, when B works on first day. How many days does A alone take finish the work? a. 1112 days b. 15 days c. 18 days d. 21 days
View SolutionAmit and Sumit can plough a field in 4 days. Sumit alone can plough the field in 6 days. In how many days will Amit alone plough the field? a. 10 days b. 12 days c. 15 days d. 14 days
View Solution8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10days b. 12 days c. 14 days d. 16 days e. none of these
View SolutionA team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8 days b. 12 days c. 9 days d. 10 days
View SolutionX can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work ? 1313 days b. 15 days c. 20 days d. 56 days
View SolutionA man and a boy together can do a certain amount of digging in 40 days. Their speeds in digging are in the ratio of 8 : 5. How many days will the boy take to complete, the work it engaged alone? 2 days b. 68 days c. 80 days d. 104 days
View Solution