Doubtnut Promotions Sticky

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?

A

40

B

50

C

48

D

56

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
    How many men can be discharged now so that the work may finish in time?

    A48
    B56
    C40
    D50
  • Question 1 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

    A48
    B56
    C40
    D50
  • Question 1 - Select One

    A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :

    A45
    B40
    C35
    D30
  • Question 1 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men
  • Question 1 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45
  • Question 1 - Select One

    90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

    A10
    B15
    C20
    D25
  • Question 1 - Select One

    A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

    A16
    B15
    C20
    D25
  • Question 1 - Select One

    A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?

    A60
    B80
    C20
    D25

Similar Questions