A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?

A

10 days

B

20 days

C

9411days

D

30 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will first determine the work done by A, B, and C in one day, and then calculate how long it takes for them to finish the work given the conditions stated.

Step 1: Calculate the work done by A, B, and C in one day.

- A can complete the work in 16 days, so the work done by A in one day is:
Work done by A in 1 day=116

- B can complete the work in 32 days, so the work done by B in one day is:
Work done by B in 1 day=132

- C can complete the work in 48 days, so the work done by C in one day is:
Work done by C in 1 day=148

Step 2: Calculate the total work done by A, B, and C together in one day.

To find the total work done by A, B, and C in one day, we add their individual contributions:
Total work done in 1 day=116+132+148

To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 32, and 48 is 96.

Converting each fraction:
116=696,132=396,148=296

Now, adding them:
Total work done in 1 day=696+396+296=1196

Step 3: Let the total number of days taken to finish the work be x.

Since A works continuously until the end, and C leaves 2 days before the work is finished while B leaves 1 day before, we can set up the equation based on the work done.

- A works for x days.
- B works for x1 days.
- C works for x2 days.

The total work done can be expressed as:
Work done by A+Work done by B+Work done by C=1
Substituting the work done:
x16+x132+x248=1

Step 4: Solve the equation.

To solve this equation, we will first find a common denominator, which is 96:
6x96+3(x1)96+2(x2)96=1

Combining the fractions:
6x+3(x1)+2(x2)96=1

Expanding:
6x+3x3+2x4=96
11x7=96
11x=103
x=103119.36

Step 5: Calculate the time taken to finish the work.

Since x represents the total days taken to finish the work, we round it to the nearest whole number. Thus, the work is finished in approximately 9 days.

Final Answer:
The work is finished in approximately 9 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?

    A3 days
    B4 days
    C5 days
    D8 days
  • A, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?

    A8 days
    B5 days
    C6 days
    D7 days
  • A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these