A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?
10 days
20 days
9411days
30 days
The correct Answer is:C
To solve the problem, we will first determine the work done by A, B, and C in one day, and then calculate how long it takes for them to finish the work given the conditions stated.
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 16 days, so the work done by A in one day is:
Work done by A in 1 day=116
- B can complete the work in 32 days, so the work done by B in one day is:
Work done by B in 1 day=132
- C can complete the work in 48 days, so the work done by C in one day is:
Work done by C in 1 day=148
Step 2: Calculate the total work done by A, B, and C together in one day.
To find the total work done by A, B, and C in one day, we add their individual contributions:
Total work done in 1 day=116+132+148
To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 32, and 48 is 96.
Converting each fraction:
116=696,132=396,148=296
Now, adding them:
Total work done in 1 day=696+396+296=1196
Step 3: Let the total number of days taken to finish the work be x.
Since A works continuously until the end, and C leaves 2 days before the work is finished while B leaves 1 day before, we can set up the equation based on the work done.
- A works for x days.
- B works for x−1 days.
- C works for x−2 days.
The total work done can be expressed as:
Work done by A+Work done by B+Work done by C=1
Substituting the work done:
x16+x−132+x−248=1
Step 4: Solve the equation.
To solve this equation, we will first find a common denominator, which is 96:
6x96+3(x−1)96+2(x−2)96=1
Combining the fractions:
6x+3(x−1)+2(x−2)96=1
Expanding:
6x+3x−3+2x−4=96
11x−7=96
11x=103
x=10311≈9.36
Step 5: Calculate the time taken to finish the work.
Since x represents the total days taken to finish the work, we round it to the nearest whole number. Thus, the work is finished in approximately 9 days.
Final Answer:
The work is finished in approximately 9 days.
---
Work done by A in 1 day=116
Work done by B in 1 day=132
Work done by C in 1 day=148
Total work done in 1 day=116+132+148
116=696,132=396,148=296
Total work done in 1 day=696+396+296=1196
- B works for x−1 days.
- C works for x−2 days.
Work done by A+Work done by B+Work done by C=1
Substituting the work done:
x16+x−132+x−248=1
6x96+3(x−1)96+2(x−2)96=1
6x+3(x−1)+2(x−2)96=1
6x+3x−3+2x−4=96
11x−7=96
11x=103
x=10311≈9.36
The work is finished in approximately 9 days.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION68videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
A, B and C can finish a piece of work in 16 days, 20 days and 24 days respectively. They started working together. How many days before B should leave the work so that work must complete in 7 days?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?
A3 daysB4 daysC5 daysD8 days - Question 2 - Select One
A, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?
A8 daysB5 daysC6 daysD7 days - Question 3 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is
View Solution