A can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
9 days
8 days
10 days
12 days
The correct Answer is:A
To solve the problem step by step, we will follow the given information about A and B's work rates and the total time taken to complete the work.
Step 1: Determine the work rates of A and B
- A can complete the work in 45 days, so A's work rate (efficiency) is:
Efficiency of A=1 work45 days=145 work/day
- B can complete the work in 40 days, so B's work rate (efficiency) is:
Efficiency of B=1 work40 days=140 work/day
Step 2: Find the LCM of the days to determine the total work
- The LCM of 45 and 40 is 360. We can consider the total work as 360 units.
Step 3: Calculate the efficiencies in terms of work units
- A's efficiency in units of work is:
Efficiency of A=360 units45 days=8 units/day
- B's efficiency in units of work is:
Efficiency of B=360 units40 days=9 units/day
Step 4: Calculate the total work done by B in 32 days
- Since both A and B start the work together and the total work is completed in 32 days, we can calculate the work done by B:
Work done by B=Efficiency of B×Time=9 units/day×32 days=288 units
Step 5: Determine the remaining work
- The total work is 360 units, so the remaining work that A must complete is:
Remaining work=360 units−288 units=72 units
Step 6: Calculate the time taken by A to complete the remaining work
- A's efficiency is 8 units/day, so the time taken by A to complete the remaining 72 units of work is:
Time taken by A=Remaining workEfficiency of A=72 units8 units/day=9 days
Step 7: Conclusion
- Since A worked for 9 days before leaving the work, we conclude that A worked for 9 days.
---
- A can complete the work in 45 days, so A's work rate (efficiency) is:
Efficiency of A=1 work45 days=145 work/day
Efficiency of B=1 work40 days=140 work/day
- The LCM of 45 and 40 is 360. We can consider the total work as 360 units.
- A's efficiency in units of work is:
Efficiency of A=360 units45 days=8 units/day
- B's efficiency in units of work is:
Efficiency of B=360 units40 days=9 units/day
- Since both A and B start the work together and the total work is completed in 32 days, we can calculate the work done by B:
Work done by B=Efficiency of B×Time=9 units/day×32 days=288 units
- The total work is 360 units, so the remaining work that A must complete is:
Remaining work=360 units−288 units=72 units
- A's efficiency is 8 units/day, so the time taken by A to complete the remaining 72 units of work is:
Time taken by A=Remaining workEfficiency of A=72 units8 units/day=9 days
- Since A worked for 9 days before leaving the work, we conclude that A worked for 9 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View SolutionA can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
A12 daysB8 daysC9 daysD1012 days - Question 2 - Select One
A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9 - Question 3 - Select One
Krishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?
A413B314C235D325
A can do a work in 15 days and B in 30 days. If they work on it together, then in how many days will they be able to do 50% of the work?
View SolutionKrishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View SolutionA can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
View Solution