Doubtnut Promotions Sticky

A can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?

A

9 days

B

8 days

C

10 days

D

12 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow the given information about A and B's work rates and the total time taken to complete the work.

Step 1: Determine the work rates of A and B
- A can complete the work in 45 days, so A's work rate (efficiency) is:
Efficiency of A=1 work45 days=145 work/day

- B can complete the work in 40 days, so B's work rate (efficiency) is:
Efficiency of B=1 work40 days=140 work/day

Step 2: Find the LCM of the days to determine the total work
- The LCM of 45 and 40 is 360. We can consider the total work as 360 units.

Step 3: Calculate the efficiencies in terms of work units
- A's efficiency in units of work is:
Efficiency of A=360 units45 days=8 units/day
- B's efficiency in units of work is:
Efficiency of B=360 units40 days=9 units/day

Step 4: Calculate the total work done by B in 32 days
- Since both A and B start the work together and the total work is completed in 32 days, we can calculate the work done by B:
Work done by B=Efficiency of B×Time=9 units/day×32 days=288 units

Step 5: Determine the remaining work
- The total work is 360 units, so the remaining work that A must complete is:
Remaining work=360 units288 units=72 units

Step 6: Calculate the time taken by A to complete the remaining work
- A's efficiency is 8 units/day, so the time taken by A to complete the remaining 72 units of work is:
Time taken by A=Remaining workEfficiency of A=72 units8 units/day=9 days

Step 7: Conclusion
- Since A worked for 9 days before leaving the work, we conclude that A worked for 9 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?

    A12 days
    B8 days
    C9 days
    D1012 days
  • Question 2 - Select One

    A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

    A10
    B8
    C12
    D9
  • Question 3 - Select One

    Krishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?

    A413
    B314
    C235
    D325