A can do a piece of work in 10 days. B can do it in 24 days. If C also works with them then it takes only 6 days to complete the whole work. In how many days C alone can complete the whole work?

A

25

B

40

C

50

D

75

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the total work
We will take the total work to be the least common multiple (LCM) of the days taken by A, B, and the combined work with C. The days are 10, 24, and 6.

LCM of 10, 24, and 6:
- The prime factorization of 10 is 21×51
- The prime factorization of 24 is 23×31
- The prime factorization of 6 is 21×31

The LCM will take the highest power of each prime:
- 23 from 24
- 31 from 24
- 51 from 10

So, LCM = 23×31×51=120.

Total work = 120 units.

Step 2: Calculate the work done by A and B in one day
- A can complete the work in 10 days, so in one day, A does:
Work done by A in 1 day=120 units10 days=12 units/day

- B can complete the work in 24 days, so in one day, B does:
Work done by B in 1 day=120 units24 days=5 units/day

Step 3: Calculate the combined work done by A, B, and C in one day
When A, B, and C work together, they complete the work in 6 days. Therefore, the combined work done in one day is:
Work done by A, B, and C in 1 day=120 units6 days=20 units/day

Step 4: Find the work done by C in one day
Now we can set up the equation:
Work done by A+Work done by B+Work done by C=Total work done in 1 day
Substituting the known values:
12+5+C=20
Thus,
C=20(12+5)=2017=3 units/day

Step 5: Calculate the time taken by C to complete the work alone
Now we need to find out how many days C will take to complete the total work of 120 units at the rate of 3 units per day:
Time taken by C=Total workC's efficiency=120 units3 units/day=40 days

Final Answer
C alone can complete the whole work in 40 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

    A10.5
    B8
    C283
    D9
  • A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    A10.5
    B8
    C8.4
    D9
  • A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?

    A6
    B4
    C5
    D10