Ajit is 3 times as efficient as Bablu, then the ratio of number of days required by each to work alone, completely?
3:1
1:3
6:3
3:6
The correct Answer is:B
To solve the problem, we need to find the ratio of the number of days required by Ajit and Bablu to complete a work alone, given that Ajit is 3 times as efficient as Bablu.
1. Define the Efficiency:
- Let the efficiency of Bablu be EB=1 unit of work per day.
- Since Ajit is 3 times as efficient as Bablu, his efficiency will be EA=3 units of work per day.
2. Understanding the Relationship:
- Efficiency is defined as the amount of work done per unit time. Therefore, if the efficiency increases, the time taken to complete the work decreases.
- The formula relating efficiency and time is:
Efficiency=WorkTime
- If we consider the total work to be constant, the efficiency and time are inversely proportional.
3. Setting Up the Ratio of Efficiencies:
- The ratio of the efficiencies of Ajit and Bablu can be expressed as:
EAEB=31
4. Finding the Ratio of Time Taken:
- Since time is inversely proportional to efficiency, the ratio of the time taken by Ajit (T_A) to the time taken by Bablu (T_B) will be the inverse of their efficiency ratio:
TATB=13
5. Expressing the Ratio:
- Therefore, the ratio of the number of days required by Ajit to Bablu is:
TA:TB=1:3
Final Answer:
The ratio of the number of days required by Ajit and Bablu to work alone is 1:3.
---
- Let the efficiency of Bablu be EB=1 unit of work per day.
- Since Ajit is 3 times as efficient as Bablu, his efficiency will be EA=3 units of work per day.
- Efficiency is defined as the amount of work done per unit time. Therefore, if the efficiency increases, the time taken to complete the work decreases.
- The formula relating efficiency and time is:
Efficiency=WorkTime
- If we consider the total work to be constant, the efficiency and time are inversely proportional.
- The ratio of the efficiencies of Ajit and Bablu can be expressed as:
EAEB=31
- Since time is inversely proportional to efficiency, the ratio of the time taken by Ajit (T_A) to the time taken by Bablu (T_B) will be the inverse of their efficiency ratio:
TATB=13
- Therefore, the ratio of the number of days required by Ajit to Bablu is:
TA:TB=1:3
The ratio of the number of days required by Ajit and Bablu to work alone is 1:3.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
Knowledge Check
A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
A50B60C54D45450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
A50B60C54D45
If 'A' is 6 times more efficient than 'B', 'B' takes 32 days to complete the task, then find the number of days required to finish the whole work by 'A' and 'B' working together.
View SolutionA is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.
View SolutionA, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
View SolutionA, B and C can individually complete a piece of work in 24 days, 15 days and 12 days. respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is :
View SolutionWorking efficiencies of P and Q for completing a piece of work are in the ratio 3:4. The number of days to be taken by them to complete the work will be in the ratio
View Solution