Ajit is 3 times as efficient as Bablu, then the ratio of number of days required by each to work alone, completely?

A

3:1

B

1:3

C

6:3

D

3:6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to find the ratio of the number of days required by Ajit and Bablu to complete a work alone, given that Ajit is 3 times as efficient as Bablu.

1. Define the Efficiency:
- Let the efficiency of Bablu be EB=1 unit of work per day.
- Since Ajit is 3 times as efficient as Bablu, his efficiency will be EA=3 units of work per day.

2. Understanding the Relationship:
- Efficiency is defined as the amount of work done per unit time. Therefore, if the efficiency increases, the time taken to complete the work decreases.
- The formula relating efficiency and time is:
Efficiency=WorkTime
- If we consider the total work to be constant, the efficiency and time are inversely proportional.

3. Setting Up the Ratio of Efficiencies:
- The ratio of the efficiencies of Ajit and Bablu can be expressed as:
EAEB=31

4. Finding the Ratio of Time Taken:
- Since time is inversely proportional to efficiency, the ratio of the time taken by Ajit (T_A) to the time taken by Bablu (T_B) will be the inverse of their efficiency ratio:
TATB=13

5. Expressing the Ratio:
- Therefore, the ratio of the number of days required by Ajit to Bablu is:
TA:TB=1:3

Final Answer:
The ratio of the number of days required by Ajit and Bablu to work alone is 1:3.

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42
  • 450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

    A50
    B60
    C54
    D45
  • 450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

    A50
    B60
    C54
    D45