Doubtnut Promotions Sticky

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

A

4

B

5

C

6

D

none of these

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will use the relationship between the number of workers, the number of days, and the amount of work done.

Step 1: Understand the given data
We know that:
- 30 persons can complete the work in 24 days.

Step 2: Calculate the total work in terms of person-days
Total work can be calculated as:
Total Work=Number of Persons×Number of Days
So, in this case:
Total Work=30 persons×24 days=720 person-days

Step 3: Determine the number of persons required to complete the work in 20 days
Let M2 be the number of persons required to complete the same work in 20 days. We can set up the equation:
M2×20 days=720 person-days
To find M2, we rearrange the equation:
M2=720 person-days20 days=36 persons

Step 4: Calculate how many more persons are needed
We need to find out how many more persons are required compared to the original 30 persons:
More persons required=M2M1=3630=6

Final Answer
Thus, the number of additional persons required to complete the work in 20 days is 6 persons.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?

    A4
    B5
    C3
    Dnone of these
  • Question 2 - Select One

    12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?

    A192
    B190
    C180
    D144
  • Question 3 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10