20 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?
20
12
18
40
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done by a certain number of persons in a given number of days.
Step 1: Determine the total work
Given that 20 persons completed 13 of the work in 24 days, we can denote the total work as 1 unit. Therefore, the work done by 20 persons in 24 days is:
W1=13
Step 2: Calculate the total work done by one person in one day
The work done by 20 persons in 24 days can be expressed as:
Work done by 20 persons in 24 days=20×24=480 person-days
Since this is equal to 13 of the total work, we can find the total work in person-days:
Total work in person-days=480×3=1440 person-days
Step 3: Determine the remaining work
The remaining work, which is W2, is:
W2=1−13=23
Step 4: Set up the equation for the remaining work
Let x be the number of additional persons required. The total number of persons working to complete the remaining work will be 20+x. They need to complete 23 of the work in 12 days. The equation for work done can be set up as:
(20+x)×12=23×1440
Step 5: Calculate the right-hand side
Calculating the right-hand side:
23×1440=960 person-days
Step 6: Substitute and solve for x
Now substituting back into the equation:
(20+x)×12=960
Dividing both sides by 12:
20+x=96012=80
Now, solving for x:
x=80−20=60
Conclusion
Thus, the number of additional persons required to finish the remaining work in the next 12 days is:
60
---
Given that 20 persons completed 13 of the work in 24 days, we can denote the total work as 1 unit. Therefore, the work done by 20 persons in 24 days is:
W1=13
The work done by 20 persons in 24 days can be expressed as:
Work done by 20 persons in 24 days=20×24=480 person-days
Since this is equal to 13 of the total work, we can find the total work in person-days:
Total work in person-days=480×3=1440 person-days
The remaining work, which is W2, is:
W2=1−13=23
Let x be the number of additional persons required. The total number of persons working to complete the remaining work will be 20+x. They need to complete 23 of the work in 12 days. The equation for work done can be set up as:
(20+x)×12=23×1440
Calculating the right-hand side:
23×1440=960 person-days
Now substituting back into the equation:
(20+x)×12=960
Dividing both sides by 12:
20+x=96012=80
Now, solving for x:
x=80−20=60
Thus, the number of additional persons required to finish the remaining work in the next 12 days is:
60
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)55videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Questions
20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution
Knowledge Check
- Question 1 - Select One
20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
A20B12C18D40 - Question 2 - Select One
100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
A100B60C80D40 - Question 3 - Select One
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24
30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?
View Solution15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?
View SolutionTwelve persons can do a piece of work in 20 days. How many persons are required to do the same in 24 days?
View SolutionTwelve persons can do a piece of work in days. How many persons are required to do the same in 24 days?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View Solution