A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
32
36
42
40
The correct Answer is:A
To solve the problem step by step, we can follow these calculations:
Step 1: Define the Variables
Let the original number of men in the group be x.
Step 2: Calculate the Total Work
The total work can be expressed in terms of man-days. If x men can complete the job in 20 days, the total work W is:
W=x×20
Step 3: Account for the Men Who Did Not Turn Up
Since 12 men did not turn up, the number of men who actually worked is:
x−12
Step 4: Calculate the Work Done by Remaining Men
The remaining men completed the job in 32 days. Therefore, the work done can also be expressed as:
W=(x−12)×32
Step 5: Set the Two Expressions for Work Equal
Since both expressions represent the same total work, we can set them equal to each other:
x×20=(x−12)×32
Step 6: Expand and Rearrange the Equation
Expanding the right side gives:
20x=32x−384
Now, rearranging the equation to isolate x:
20x−32x=−384
−12x=−384
Step 7: Solve for x
Dividing both sides by -12 gives:
x=38412=32
Conclusion
The original number of men in the group was 32.
---
Let the original number of men in the group be x.
The total work can be expressed in terms of man-days. If x men can complete the job in 20 days, the total work W is:
W=x×20
Since 12 men did not turn up, the number of men who actually worked is:
x−12
The remaining men completed the job in 32 days. Therefore, the work done can also be expressed as:
W=(x−12)×32
Since both expressions represent the same total work, we can set them equal to each other:
x×20=(x−12)×32
Expanding the right side gives:
20x=32x−384
Now, rearranging the equation to isolate x:
20x−32x=−384
−12x=−384
Dividing both sides by -12 gives:
x=38412=32
The original number of men in the group was 32.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
Knowledge Check
A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A24B20C16D18Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
A10B15C12D14
A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View SolutionA group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
View SolutionA group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionA group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?
View Solution