A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
48
56
40
50
The correct Answer is:B
To solve the problem step by step, we will follow the reasoning laid out in the video transcript.
Step 1: Understand the total work and the initial setup
The contractor has a total of 124 days to complete the work with 120 men.
Step 2: Calculate the work done in the first 64 days
In the first 64 days, the contractor completed 23 of the work.
Step 3: Determine the remaining work
The remaining work after 64 days is:
Remaining work=1−23=13
Step 4: Calculate the remaining days
The total time is 124 days, and 64 days have already been used. Therefore, the remaining days are:
Remaining days=124−64=60 days
Step 5: Set up the equation for the remaining work
Let x be the number of men to be discharged. The number of men remaining after discharging x men will be:
120−x
The work done by 120−x men in the remaining 60 days must equal the remaining 13 of the work.
Step 6: Calculate the work done by the original setup
The work done by 120 men in 64 days can be expressed as:
Work done=120 men×64 days
Step 7: Set up the equation for the remaining work
The work done by 120−x men in 60 days is:
Work done=(120−x) men×60 days
Setting the work done equal to the remaining work:
(120−x)×60=13×(120×124)
Step 8: Calculate the total work
The total work can be calculated as:
Total work=120 men×124 days=14880 man-days
Thus, the remaining work is:
13×14880=4960 man-days
Step 9: Set up the final equation
Now we can equate:
(120−x)×60=4960
Step 10: Solve for x
Expanding the equation gives:
7200−60x=4960
Rearranging gives:
60x=7200−4960
60x=2240
x=224060=37.33
Since x must be a whole number, we round it to 37.
Conclusion
The contractor can discharge 37 men to finish the work on time.
The contractor has a total of 124 days to complete the work with 120 men.
In the first 64 days, the contractor completed 23 of the work.
The remaining work after 64 days is:
Remaining work=1−23=13
The total time is 124 days, and 64 days have already been used. Therefore, the remaining days are:
Remaining days=124−64=60 days
Let x be the number of men to be discharged. The number of men remaining after discharging x men will be:
120−x
The work done by 120−x men in the remaining 60 days must equal the remaining 13 of the work.
The work done by 120 men in 64 days can be expressed as:
Work done=120 men×64 days
The work done by 120−x men in 60 days is:
Work done=(120−x) men×60 days
Setting the work done equal to the remaining work:
(120−x)×60=13×(120×124)
The total work can be calculated as:
Total work=120 men×124 days=14880 man-days
Thus, the remaining work is:
13×14880=4960 man-days
Now we can equate:
(120−x)×60=4960
Expanding the equation gives:
7200−60x=4960
Rearranging gives:
60x=7200−4960
60x=2240
x=224060=37.33
Since x must be a whole number, we round it to 37.
The contractor can discharge 37 men to finish the work on time.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
A48B56C40D50 - Question 2 - Select One
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
How many men can be discharged now so that the work may finish in time?A48B56C40D50 - Question 3 - Select One
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :
A45B40C35D30
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
View Solution90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
View Solution