Doubtnut Promotions Sticky

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

A

48

B

56

C

40

D

50

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow the reasoning laid out in the video transcript.

Step 1: Understand the total work and the initial setup
The contractor has a total of 124 days to complete the work with 120 men.

Step 2: Calculate the work done in the first 64 days
In the first 64 days, the contractor completed 23 of the work.

Step 3: Determine the remaining work
The remaining work after 64 days is:
Remaining work=123=13

Step 4: Calculate the remaining days
The total time is 124 days, and 64 days have already been used. Therefore, the remaining days are:
Remaining days=12464=60 days

Step 5: Set up the equation for the remaining work
Let x be the number of men to be discharged. The number of men remaining after discharging x men will be:
120x
The work done by 120x men in the remaining 60 days must equal the remaining 13 of the work.

Step 6: Calculate the work done by the original setup
The work done by 120 men in 64 days can be expressed as:
Work done=120 men×64 days

Step 7: Set up the equation for the remaining work
The work done by 120x men in 60 days is:
Work done=(120x) men×60 days
Setting the work done equal to the remaining work:
(120x)×60=13×(120×124)

Step 8: Calculate the total work
The total work can be calculated as:
Total work=120 men×124 days=14880 man-days
Thus, the remaining work is:
13×14880=4960 man-days

Step 9: Set up the final equation
Now we can equate:
(120x)×60=4960

Step 10: Solve for x
Expanding the equation gives:
720060x=4960
Rearranging gives:
60x=72004960
60x=2240
x=224060=37.33
Since x must be a whole number, we round it to 37.

Conclusion
The contractor can discharge 37 men to finish the work on time.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?

    A48
    B56
    C40
    D50
  • Question 2 - Select One

    A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 23 of the work.
    How many men can be discharged now so that the work may finish in time?

    A48
    B56
    C40
    D50
  • Question 3 - Select One

    A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :

    A45
    B40
    C35
    D30