A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A

5 days

B

6 days

C

10 days

D

1012 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will follow these steps:

1. Determine the work done by A, B, and C in one day:
- A can finish the work in 24 days, so A's work in one day = 124.
- B can finish the work in 9 days, so B's work in one day = 19.
- C can finish the work in 12 days, so C's work in one day = 112.

2. Calculate the combined work done by B and C in one day:
- Combined work of B and C in one day = 19+112.
- To add these fractions, we need a common denominator. The least common multiple of 9 and 12 is 36.
- Convert the fractions:
- 19=436
- 112=336
- So, combined work = 436+336=736.

3. Calculate the total work done by B and C in 3 days:
- Work done by B and C in 3 days = 3×736=2136=712.

4. Determine the remaining work after B and C leave:
- Total work is considered as 1 (whole work).
- Remaining work = Total work - Work done by B and C = 1712=512.

5. Calculate how long it will take A to finish the remaining work:
- A's work in one day = 124.
- To find the number of days A needs to finish 512 of the work, we set up the equation:
Days=Remaining WorkA's Work in one day=512124.
- This simplifies to:
Days=512×24=5×2412=12012=10.

Thus, A will take 10 days to finish the remaining work.

Updated on:7/8/2024
|


Similar Questions


Knowledge Check

  • A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in

    A10 days
    B1012days
    C5days
    D6days
  • A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B9 days
    C10 days
    D13 days
  • A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

    A10 days
    B12 days
    C15 days
    D16 days