A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
5 days
6 days
10 days
1012 days
The correct Answer is:C
To solve the problem, we will follow these steps:
1. Determine the work done by A, B, and C in one day:
- A can finish the work in 24 days, so A's work in one day = 124.
- B can finish the work in 9 days, so B's work in one day = 19.
- C can finish the work in 12 days, so C's work in one day = 112.
2. Calculate the combined work done by B and C in one day:
- Combined work of B and C in one day = 19+112.
- To add these fractions, we need a common denominator. The least common multiple of 9 and 12 is 36.
- Convert the fractions:
- 19=436
- 112=336
- So, combined work = 436+336=736.
3. Calculate the total work done by B and C in 3 days:
- Work done by B and C in 3 days = 3×736=2136=712.
4. Determine the remaining work after B and C leave:
- Total work is considered as 1 (whole work).
- Remaining work = Total work - Work done by B and C = 1−712=512.
5. Calculate how long it will take A to finish the remaining work:
- A's work in one day = 124.
- To find the number of days A needs to finish 512 of the work, we set up the equation:
Days=Remaining WorkA's Work in one day=512124.
- This simplifies to:
Days=512×24=5×2412=12012=10.
Thus, A will take 10 days to finish the remaining work.
- A can finish the work in 24 days, so A's work in one day = 124.
- B can finish the work in 9 days, so B's work in one day = 19.
- C can finish the work in 12 days, so C's work in one day = 112.
- Combined work of B and C in one day = 19+112.
- To add these fractions, we need a common denominator. The least common multiple of 9 and 12 is 36.
- Convert the fractions:
- 19=436
- 112=336
- So, combined work = 436+336=736.
- Work done by B and C in 3 days = 3×736=2136=712.
- Total work is considered as 1 (whole work).
- Remaining work = Total work - Work done by B and C = 1−712=512.
- A's work in one day = 124.
- To find the number of days A needs to finish 512 of the work, we set up the equation:
Days=Remaining WorkA's Work in one day=512124.
- This simplifies to:
Days=512×24=5×2412=12012=10.
Similar Questions
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View SolutionA can complete a piece of work In 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View Solution
Knowledge Check
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
A10 daysB1012daysC5daysD6daysA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB9 daysC10 daysD13 daysA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 days
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View SolutionA can complete a work in 24 days, B in 32 days and C in 64 days. They start together. A works for 6 days and leaves and B leaves 6 days before the work is finished. In how many days was the work finished?
View Solution