S,T and U can complete a work in 40,48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work along. What is the share of S ( in Rs. ) from total money ?
4000
4320
4500
4860
The correct Answer is:4
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the total work
The total work can be calculated using the Least Common Multiple (LCM) of the days taken by S, T, and U to complete the work.
- S can complete the work in 40 days.
- T can complete the work in 48 days.
- U can complete the work in 60 days.
To find the LCM of 40, 48, and 60:
- Prime factorization:
- 40 = 2^3 * 5
- 48 = 2^4 * 3
- 60 = 2^2 * 3 * 5
The LCM will take the highest power of each prime factor:
- LCM = 2^4 * 3^1 * 5^1 = 240
Thus, the total work is 240 units.
Step 2: Calculate the work done by each person in one day
Now, we will calculate how much work each person can do in one day.
- Work done by S in one day = Total work / Days taken by S = 240 / 40 = 6 units
- Work done by T in one day = Total work / Days taken by T = 240 / 48 = 5 units
- Work done by U in one day = Total work / Days taken by U = 240 / 60 = 4 units
Step 3: Calculate the combined work done in one day
The combined work done by S, T, and U in one day is:
- Total work done in one day = Work by S + Work by T + Work by U = 6 + 5 + 4 = 15 units
Step 4: Determine the total time taken to complete the work
Let X be the total number of days taken to complete the work.
- S worked for X days.
- T worked for (X - 2) days (since T left 2 days before completion).
- U worked for (X - 5) days (since U left 5 days before completion).
The equation for the total work done is:
6X+5(X−2)+4(X−5)=240
Expanding this:
6X+5X−10+4X−20=240
15X−30=240
15X=270
X=18
Step 5: Calculate the work done by each person
Now we can calculate how much work each person completed:
- Work done by S = 6 * 18 = 108 units
- Work done by T = 5 * (18 - 2) = 5 * 16 = 80 units
- Work done by U = 4 * (18 - 5) = 4 * 13 = 52 units
Step 6: Calculate the total work done
Total work done = Work by S + Work by T + Work by U = 108 + 80 + 52 = 240 units (which confirms our calculations).
Step 7: Calculate the share of S from the total money
The total money received is Rs. 10800. The share of each person is proportional to the work done.
- Total work done = 240 units
- Share of S = (Work done by S / Total work) * Total money
Share of S=(108240)×10800
Share of S=108×10800240
Share of S=1166400240=4860
Final Answer
The share of S from the total money is Rs. 4860.
The total work can be calculated using the Least Common Multiple (LCM) of the days taken by S, T, and U to complete the work.
- T can complete the work in 48 days.
- U can complete the work in 60 days.
- Prime factorization:
- 40 = 2^3 * 5
- 48 = 2^4 * 3
- 60 = 2^2 * 3 * 5
- LCM = 2^4 * 3^1 * 5^1 = 240
Now, we will calculate how much work each person can do in one day.
- Work done by T in one day = Total work / Days taken by T = 240 / 48 = 5 units
- Work done by U in one day = Total work / Days taken by U = 240 / 60 = 4 units
The combined work done by S, T, and U in one day is:
- Total work done in one day = Work by S + Work by T + Work by U = 6 + 5 + 4 = 15 units
Let X be the total number of days taken to complete the work.
- T worked for (X - 2) days (since T left 2 days before completion).
- U worked for (X - 5) days (since U left 5 days before completion).
6X+5(X−2)+4(X−5)=240
6X+5X−10+4X−20=240
15X−30=240
15X=270
X=18
Now we can calculate how much work each person completed:
- Work done by S = 6 * 18 = 108 units
- Work done by T = 5 * (18 - 2) = 5 * 16 = 80 units
- Work done by U = 4 * (18 - 5) = 4 * 13 = 52 units
Total work done = Work by S + Work by T + Work by U = 108 + 80 + 52 = 240 units (which confirms our calculations).
The total money received is Rs. 10800. The share of each person is proportional to the work done.
- Share of S = (Work done by S / Total work) * Total money
Share of S=(108240)×10800
Share of S=108×10800240
Share of S=1166400240=4860
The share of S from the total money is Rs. 4860.
Similar Questions
A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8View Solution
Knowledge Check
- Question 1 - Select One
S, T and U can complete a work In 40, 48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work alone. What is the share of Sin Rs.) from total money?
A4000B4320C4500D4860 - Question 2 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these - Question 3 - Select One
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionP can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View Solution