Doubtnut Promotions Sticky

S,T and U can complete a work in 40,48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work along. What is the share of S ( in Rs. ) from total money ?

A

4000

B

4320

C

4500

D

4860

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:4


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the total work
The total work can be calculated using the Least Common Multiple (LCM) of the days taken by S, T, and U to complete the work.

- S can complete the work in 40 days.
- T can complete the work in 48 days.
- U can complete the work in 60 days.

To find the LCM of 40, 48, and 60:
- Prime factorization:
- 40 = 2^3 * 5
- 48 = 2^4 * 3
- 60 = 2^2 * 3 * 5

The LCM will take the highest power of each prime factor:
- LCM = 2^4 * 3^1 * 5^1 = 240

Thus, the total work is 240 units.

Step 2: Calculate the work done by each person in one day
Now, we will calculate how much work each person can do in one day.

- Work done by S in one day = Total work / Days taken by S = 240 / 40 = 6 units
- Work done by T in one day = Total work / Days taken by T = 240 / 48 = 5 units
- Work done by U in one day = Total work / Days taken by U = 240 / 60 = 4 units

Step 3: Calculate the combined work done in one day
The combined work done by S, T, and U in one day is:
- Total work done in one day = Work by S + Work by T + Work by U = 6 + 5 + 4 = 15 units

Step 4: Determine the total time taken to complete the work
Let X be the total number of days taken to complete the work.

- S worked for X days.
- T worked for (X - 2) days (since T left 2 days before completion).
- U worked for (X - 5) days (since U left 5 days before completion).

The equation for the total work done is:
6X+5(X2)+4(X5)=240

Expanding this:
6X+5X10+4X20=240
15X30=240
15X=270
X=18

Step 5: Calculate the work done by each person
Now we can calculate how much work each person completed:
- Work done by S = 6 * 18 = 108 units
- Work done by T = 5 * (18 - 2) = 5 * 16 = 80 units
- Work done by U = 4 * (18 - 5) = 4 * 13 = 52 units

Step 6: Calculate the total work done
Total work done = Work by S + Work by T + Work by U = 108 + 80 + 52 = 240 units (which confirms our calculations).

Step 7: Calculate the share of S from the total money
The total money received is Rs. 10800. The share of each person is proportional to the work done.

- Total work done = 240 units
- Share of S = (Work done by S / Total work) * Total money
Share of S=(108240)×10800
Share of S=108×10800240
Share of S=1166400240=4860

Final Answer
The share of S from the total money is Rs. 4860.

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    S, T and U can complete a work In 40, 48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work alone. What is the share of Sin Rs.) from total money?

    A4000
    B4320
    C4500
    D4860
  • Question 2 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these