Doubtnut Promotions Sticky

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone?

A

24 days

B

32 days

C

40 days

D

48 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine how long B would take to complete the work alone based on the information given about the work done by A, B, and C together. Here’s a step-by-step breakdown of the solution:

Step 1: Determine the total work
We know that:
- A and B can complete the work in 12 days.
- B and C can complete the work in 8 days.
- C and A can complete the work in 6 days.

To find a common measure of work, we can take the Least Common Multiple (LCM) of the days taken by each pair to complete the work.

The LCM of 12, 8, and 6 is 24. Therefore, we can consider the total work to be 24 units.

Step 2: Calculate the work done by each pair in one day
Now we can find the work done by each pair in one day:
- Work done by A and B in one day = Total work / Days = 24 / 12 = 2 units.
- Work done by B and C in one day = Total work / Days = 24 / 8 = 3 units.
- Work done by C and A in one day = Total work / Days = 24 / 6 = 4 units.

Step 3: Set up equations based on the work done
Let:
- A's work in one day = a
- B's work in one day = b
- C's work in one day = c

From the above calculations, we can set up the following equations:
1. a+b=2 (Equation 1)
2. b+c=3 (Equation 2)
3. c+a=4 (Equation 3)

Step 4: Solve the equations
We can add all three equations:
(a+b)+(b+c)+(c+a)=2+3+4
This simplifies to:
2a+2b+2c=9
Dividing by 2 gives:
a+b+c=4.5 (Equation 4)

Now we can find the individual work rates:
From Equation 1:
c=4.5(a+b)=4.52=2.5

Substituting c back into Equation 2:
b+2.5=3
Thus,
b=32.5=0.5

Now substituting b into Equation 1:
a+0.5=2
Thus,
a=20.5=1.5

Step 5: Calculate B's time to complete the work alone
Now we have:
- A's work rate (a) = 1.5 units/day
- B's work rate (b) = 0.5 units/day
- C's work rate (c) = 2.5 units/day

To find out how long B would take to complete the entire work alone (24 units), we use the formula:
Time=Total WorkB's Work Rate
Time=240.5=48 days

Final Answer
B would take 48 days to complete the work alone.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?

    A10 days
    B20 days
    C30 days
    D40 days
  • Question 2 - Select One

    A and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?

    A20 days
    B60 days
    C30 days
    D40 days
  • Question 3 - Select One

    A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

    A60 days
    B120 days
    C80 days
    D30 days