A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone?
24 days
32 days
40 days
48 days
The correct Answer is:D
To solve the problem, we need to determine how long B would take to complete the work alone based on the information given about the work done by A, B, and C together. Here’s a step-by-step breakdown of the solution:
Step 1: Determine the total work
We know that:
- A and B can complete the work in 12 days.
- B and C can complete the work in 8 days.
- C and A can complete the work in 6 days.
To find a common measure of work, we can take the Least Common Multiple (LCM) of the days taken by each pair to complete the work.
The LCM of 12, 8, and 6 is 24. Therefore, we can consider the total work to be 24 units.
Step 2: Calculate the work done by each pair in one day
Now we can find the work done by each pair in one day:
- Work done by A and B in one day = Total work / Days = 24 / 12 = 2 units.
- Work done by B and C in one day = Total work / Days = 24 / 8 = 3 units.
- Work done by C and A in one day = Total work / Days = 24 / 6 = 4 units.
Step 3: Set up equations based on the work done
Let:
- A's work in one day = a
- B's work in one day = b
- C's work in one day = c
From the above calculations, we can set up the following equations:
1. a+b=2 (Equation 1)
2. b+c=3 (Equation 2)
3. c+a=4 (Equation 3)
Step 4: Solve the equations
We can add all three equations:
(a+b)+(b+c)+(c+a)=2+3+4
This simplifies to:
2a+2b+2c=9
Dividing by 2 gives:
a+b+c=4.5 (Equation 4)
Now we can find the individual work rates:
From Equation 1:
c=4.5−(a+b)=4.5−2=2.5
Substituting c back into Equation 2:
b+2.5=3
Thus,
b=3−2.5=0.5
Now substituting b into Equation 1:
a+0.5=2
Thus,
a=2−0.5=1.5
Step 5: Calculate B's time to complete the work alone
Now we have:
- A's work rate (a) = 1.5 units/day
- B's work rate (b) = 0.5 units/day
- C's work rate (c) = 2.5 units/day
To find out how long B would take to complete the entire work alone (24 units), we use the formula:
Time=Total WorkB's Work Rate
Time=240.5=48 days
Final Answer
B would take 48 days to complete the work alone.
---
We know that:
- A and B can complete the work in 12 days.
- B and C can complete the work in 8 days.
- C and A can complete the work in 6 days.
Now we can find the work done by each pair in one day:
- Work done by A and B in one day = Total work / Days = 24 / 12 = 2 units.
- Work done by B and C in one day = Total work / Days = 24 / 8 = 3 units.
- Work done by C and A in one day = Total work / Days = 24 / 6 = 4 units.
Let:
- A's work in one day = a
- B's work in one day = b
- C's work in one day = c
1. a+b=2 (Equation 1)
2. b+c=3 (Equation 2)
3. c+a=4 (Equation 3)
We can add all three equations:
(a+b)+(b+c)+(c+a)=2+3+4
This simplifies to:
2a+2b+2c=9
Dividing by 2 gives:
a+b+c=4.5 (Equation 4)
From Equation 1:
c=4.5−(a+b)=4.5−2=2.5
b+2.5=3
Thus,
b=3−2.5=0.5
a+0.5=2
Thus,
a=2−0.5=1.5
Now we have:
- A's work rate (a) = 1.5 units/day
- B's work rate (b) = 0.5 units/day
- C's work rate (c) = 2.5 units/day
Time=Total WorkB's Work Rate
Time=240.5=48 days
B would take 48 days to complete the work alone.
Similar Questions
A and B can do a piece of work in 10 days.B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone?
View SolutionA and B can do a piece of work in 40 days. B and C can do a piece of work in 30 days. C and A can do a piece of work in 24 days. How long would they all take to do the same work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
A10 daysB20 daysC30 daysD40 days - Question 2 - Select One
A and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?
A20 daysB60 daysC30 daysD40 days - Question 3 - Select One
A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
A60 daysB120 daysC80 daysD30 days
A and B can do a certain piece of work in 8 days, B and C can do it in 12 days and C and A can do it in 24 days. How long would B take separately to do it ?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days, then C alone can do the same work in how many days?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can each alone do the work?
View Solution