A and B can do a piece of work in 40 days. B and C can do a piece of work in 30 days. C and A can do a piece of work in 24 days. How long would they all take to do the same work?
The correct Answer is:20 days
To solve the problem, we need to find the individual work rates of A, B, and C based on the information given about their combined work rates. Here’s how to approach the problem step by step:
Step 1: Determine the work rates of A and B
A and B can complete the work in 40 days. Therefore, their combined work rate is:
Work rate of A + B=140 (work per day)
Step 2: Determine the work rates of B and C
B and C can complete the work in 30 days. Therefore, their combined work rate is:
Work rate of B + C=130 (work per day)
Step 3: Determine the work rates of C and A
C and A can complete the work in 24 days. Therefore, their combined work rate is:
Work rate of C + A=124 (work per day)
Step 4: Set up the equations
Let the work rates of A, B, and C be represented as a,b, and c respectively. We can write the following equations based on the combined work rates:
1. a+b=140
2. b+c=130
3. c+a=124
Step 5: Solve the equations
To find the individual work rates, we can add all three equations:
(a+b)+(b+c)+(c+a)=140+130+124
This simplifies to:
2a+2b+2c=140+130+124
Now, we need to find a common denominator for the right side. The least common multiple of 40, 30, and 24 is 120. Converting each fraction:
140=3120,130=4120,124=5120
Adding these gives:
3120+4120+5120=12120=110
Thus, we have:
2(a+b+c)=110⟹a+b+c=120
Step 6: Calculate the time taken by A, B, and C together
The combined work rate of A, B, and C is 120 work per day. Therefore, the time taken to complete the work when all three work together is:
Time=1Work rate=1120=20 days
Final Answer
Thus, A, B, and C together can complete the work in 20 days.
A and B can complete the work in 40 days. Therefore, their combined work rate is:
Work rate of A + B=140 (work per day)
B and C can complete the work in 30 days. Therefore, their combined work rate is:
Work rate of B + C=130 (work per day)
C and A can complete the work in 24 days. Therefore, their combined work rate is:
Work rate of C + A=124 (work per day)
Let the work rates of A, B, and C be represented as a,b, and c respectively. We can write the following equations based on the combined work rates:
1. a+b=140
2. b+c=130
3. c+a=124
To find the individual work rates, we can add all three equations:
(a+b)+(b+c)+(c+a)=140+130+124
This simplifies to:
2a+2b+2c=140+130+124
Now, we need to find a common denominator for the right side. The least common multiple of 40, 30, and 24 is 120. Converting each fraction:
140=3120,130=4120,124=5120
Adding these gives:
3120+4120+5120=12120=110
Thus, we have:
2(a+b+c)=110⟹a+b+c=120
The combined work rate of A, B, and C is 120 work per day. Therefore, the time taken to complete the work when all three work together is:
Time=1Work rate=1120=20 days
Thus, A, B, and C together can complete the work in 20 days.
Topper's Solved these Questions
Similar Questions
A and B together can do a piece of work in 12 days. While B and C together can do a piece of work in 8 days. C and A together can do a piece of work in 6 days. In how many days will this work be completed by B alone?
View SolutionA and B can do a certain piece of work in 8 days, B and C can do it in 12 days and C and A can do it in 24 days. How long would B take separately to do it ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
A10 daysB20 daysC30 daysD40 days - Question 2 - Select One
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone?
A24 daysB32 daysC40 daysD48 days - Question 3 - Select One
A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:
A1113 daysB1313 daysC1645 daysD1235 days
(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA and B can do a piece of work in 10 days.B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. Calone can do the work in :
View Solution