Doubtnut Promotions Sticky

A and B can do a piece of work in 40 days. B and C can do a piece of work in 30 days. C and A can do a piece of work in 24 days. How long would they all take to do the same work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:20 days


To solve the problem, we need to find the individual work rates of A, B, and C based on the information given about their combined work rates. Here’s how to approach the problem step by step:

Step 1: Determine the work rates of A and B
A and B can complete the work in 40 days. Therefore, their combined work rate is:
Work rate of A + B=140 (work per day)

Step 2: Determine the work rates of B and C
B and C can complete the work in 30 days. Therefore, their combined work rate is:
Work rate of B + C=130 (work per day)

Step 3: Determine the work rates of C and A
C and A can complete the work in 24 days. Therefore, their combined work rate is:
Work rate of C + A=124 (work per day)

Step 4: Set up the equations
Let the work rates of A, B, and C be represented as a,b, and c respectively. We can write the following equations based on the combined work rates:
1. a+b=140
2. b+c=130
3. c+a=124

Step 5: Solve the equations
To find the individual work rates, we can add all three equations:
(a+b)+(b+c)+(c+a)=140+130+124
This simplifies to:
2a+2b+2c=140+130+124
Now, we need to find a common denominator for the right side. The least common multiple of 40, 30, and 24 is 120. Converting each fraction:
140=3120,130=4120,124=5120
Adding these gives:
3120+4120+5120=12120=110
Thus, we have:
2(a+b+c)=110a+b+c=120

Step 6: Calculate the time taken by A, B, and C together
The combined work rate of A, B, and C is 120 work per day. Therefore, the time taken to complete the work when all three work together is:
Time=1Work rate=1120=20 days

Final Answer
Thus, A, B, and C together can complete the work in 20 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?

    A10 days
    B20 days
    C30 days
    D40 days
  • Question 2 - Select One

    A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone?

    A24 days
    B32 days
    C40 days
    D48 days
  • Question 3 - Select One

    A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:

    A1113 days
    B1313 days
    C1645 days
    D1235 days