150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on.
The correct Answer is:25 days
Topper's Solved these Questions
- SEQUENCES AND SERIESBOOK - NCERT TELUGUCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.4
10 Videos
- RELATIONS AND FUNCTIONSBOOK - NCERT TELUGUCHAPTER - RELATIONS AND FUNCTIONSEXERCISE - Miscellaneous Exercise on Chapter 2
12 Videos
- SETSBOOK - NCERT TELUGUCHAPTER - SETSEXERCISE - MISCELLANEOUS EXERCISE ON CHAPTER 1
22 Videos
Similar Questions
150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View Solution
Knowledge Check
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
A24 daysB40 daysC17 daysD25 days30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :
A12B10C6Dnone of these56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?A36B48C44D42
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View Solution