A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 233 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
80
81
82
83
The correct Answer is:(b)
Let x additional men employed.
117 men were supposed to finish the whole work in
46×8=368 hours.
But 117 men complete 47 of the work in 33×8
= 264 hours
∴ 117 men could complete the work in 462 hours.
Now (117+x) men are supposed to do 37 of the work,
working 9 hours a day, in 13×9=117 hours, so as to
finish the work in time.
i.e. (117+x) men are supposed to complete the whole
work in 117×73=273 hours.
∴(117+x)×273=117×462
⇒(117+x)×7=3×462
⇒x+117=3×66=198⇒x=81
∴ Required number of additional men to finish the
work in time = 81.
Topper's Solved these Questions
Similar Questions
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
View Solution
Knowledge Check
- Question 1 - Select One
A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
A80B81C84D85 - Question 2 - Select One
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A60B56C70D42 - Question 3 - Select One
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A35B40C45DNone of these
A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View SolutionA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View Solution