Doubtnut Promotions Sticky

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 233 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83

A

80

B

81

C

82

D

83

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:(b)


Let x additional men employed.
117 men were supposed to finish the whole work in
46×8=368 hours.
But 117 men complete 47 of the work in 33×8
= 264 hours
117 men could complete the work in 462 hours.
Now (117+x) men are supposed to do 37 of the work,
working 9 hours a day, in 13×9=117 hours, so as to
finish the work in time.
i.e. (117+x) men are supposed to complete the whole
work in 117×73=273 hours.
(117+x)×273=117×462
(117+x)×7=3×462
x+117=3×66=198x=81
Required number of additional men to finish the
work in time = 81.

|
Updated on:21/07/2023

Related Playlists


Similar Questions