Doubtnut Promotions Sticky

12 men can finish a project in 20 days. 18 women can finish
the same project in 16 days and 24 children can finish it in 18
days. 8 women and 16 children worked for 9 days and then
left. In how many will 10 men coplete the remaining project ?

A

1012

B

10

C

9

D

1112

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(b)


To solve the problem step by step, we will first determine the work done by men, women, and children, and then calculate how long it will take for 10 men to complete the remaining work after 8 women and 16 children have worked for 9 days.

Step 1: Calculate the work done by men, women, and children

1. Work done by 12 men in 20 days:
- Total work = Number of men × Number of days = 12 men × 20 days = 240 man-days.

2. Work done by 18 women in 16 days:
- Total work = Number of women × Number of days = 18 women × 16 days = 288 woman-days.

3. Work done by 24 children in 18 days:
- Total work = Number of children × Number of days = 24 children × 18 days = 432 child-days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined

    A36
    B24
    C18
    Dcouldn't be determined
  • Question 2 - Select One

    3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?

    A10
    B6
    C12
    D9
  • Question 3 - Select One

    2 men can complete a piece of work in 6 days. 2 women can
    complete the same piece of work in 9 days. Where as 3
    children can complete the same piece of work in 8 days. 3
    women and 4 children worked together for 1 day. If only
    men were to finish the remaining work in day, how many
    total men would be required?

    A4
    B8
    C6
    Dcan't be determined