12 men can finish a project in 20 days. 18 women can finish
the same project in 16 days and 24 children can finish it in 18
days. 8 women and 16 children worked for 9 days and then
left. In how many will 10 men coplete the remaining project ?
1012
10
9
1112
The correct Answer is:(b)
To solve the problem step by step, we will first determine the work done by men, women, and children, and then calculate how long it will take for 10 men to complete the remaining work after 8 women and 16 children have worked for 9 days.
Step 1: Calculate the work done by men, women, and children
1. Work done by 12 men in 20 days:
- Total work = Number of men × Number of days = 12 men × 20 days = 240 man-days.
2. Work done by 18 women in 16 days:
- Total work = Number of women × Number of days = 18 women × 16 days = 288 woman-days.
3. Work done by 24 children in 18 days:
- Total work = Number of children × Number of days = 24 children × 18 days = 432 child-days.
- Total work = Number of men × Number of days = 12 men × 20 days = 240 man-days.
- Total work = Number of women × Number of days = 18 women × 16 days = 288 woman-days.
- Total work = Number of children × Number of days = 24 children × 18 days = 432 child-days.
Topper's Solved these Questions
Similar Questions
If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
View Solution
Knowledge Check
- Question 1 - Select One
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
A36B24C18Dcouldn't be determined - Question 2 - Select One
3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?
A10B6C12D9 - Question 3 - Select One
2 men can complete a piece of work in 6 days. 2 women can
complete the same piece of work in 9 days. Where as 3
children can complete the same piece of work in 8 days. 3
women and 4 children worked together for 1 day. If only
men were to finish the remaining work in day, how many
total men would be required?A4B8C6Dcan't be determined
10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionIf 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
View Solution