150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)] Solution in Gujrati
The correct Answer is:x = 17 ⇒x+8=17+8=25
Step by step video, text & image solution for 150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then 150 x = (x+8)/2 [2 xx 150 + (x+8-1)(-4)] by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
Similar Questions
For each geometric progressions find the common ratio 'r'. And then find an.
(i) 3,32,34,38,……
(ii) 2,−6,18,−54
(iii) −1,−3,−9,−27,…..
(iv) 5,2,45,825,…..04:08View SolutionWhy is tossing a coin considered to be a fair way of deciding which team should get the ball at the beginning of any game
07:28View SolutionSome points are plotted on a plane such that any three of them are non collinear. Each point is joined with all remaining points by line segments. Find the number of points if the number of line segments are 10.
08:46View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
02:36View Solution150 workers were engaged to finish a job in a certain number of days.4 workers dropped out on second day,4 more workers dropped out on the third day and so on.It took 8 more days to finish the work.Find the number of days in which the work was complete.
06:38View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
02:01View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
06:22View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
[ Let the no. of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]06:07View SolutionIf they are in G.P.Write next one terms.
a,2a, 3a, 4a,......08:23View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]05:27View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
04:01View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]05:11View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
06:02View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
06:18View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
05:20View Solution