A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?
To solve the problem step by step, we will follow these calculations:
Step 1: Understand the total work and the work done
The contractor employed 30 men to complete the project in 100 days. This means that the total work can be expressed in terms of man-days:
Total Work=Number of Men×Number of Days=30 men×100 days=3000 man-days
Step 2: Calculate the work done in 25 days
After 25 days, only 20% of the work is completed. Therefore, we can calculate the amount of work done:
Work Done=20% of Total Work=0.20×3000 man-days=600 man-days
Step 3: Calculate the remaining work
Now, we need to find out how much work is left to be completed:
Remaining Work=Total Work−Work Done=3000 man-days−600 man-days=2400 man-days
Step 4: Determine how many days are needed to complete the remaining work
The contractor still has 30 men working on the project. We can find out how many additional days (let's call it X) are required to complete the remaining work:
Remaining Work=Number of Men×Number of Days
2400 man-days=30 men×X days
Solving for X:
X=2400 man-days30 men=80 days
Step 5: Calculate the total time taken
The total time taken to complete the project will be the initial 25 days plus the additional 80 days:
Total Time=25 days+80 days=105 days
Step 6: Calculate the extra days required
The extra days required beyond the scheduled time of 100 days is:
Extra Days=Total Time−Scheduled Time=105 days−100 days=5 days
Final Answer
The contractor will require an additional 5 days beyond the scheduled time.
---
The contractor employed 30 men to complete the project in 100 days. This means that the total work can be expressed in terms of man-days:
Total Work=Number of Men×Number of Days=30 men×100 days=3000 man-days
After 25 days, only 20% of the work is completed. Therefore, we can calculate the amount of work done:
Work Done=20% of Total Work=0.20×3000 man-days=600 man-days
Now, we need to find out how much work is left to be completed:
Remaining Work=Total Work−Work Done=3000 man-days−600 man-days=2400 man-days
The contractor still has 30 men working on the project. We can find out how many additional days (let's call it X) are required to complete the remaining work:
Remaining Work=Number of Men×Number of Days
2400 man-days=30 men×X days
Solving for X:
X=2400 man-days30 men=80 days
The total time taken to complete the project will be the initial 25 days plus the additional 80 days:
Total Time=25 days+80 days=105 days
The extra days required beyond the scheduled time of 100 days is:
Extra Days=Total Time−Scheduled Time=105 days−100 days=5 days
The contractor will require an additional 5 days beyond the scheduled time.
Topper's Solved these Questions
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View Solution
Knowledge Check
A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
A15B20C25D3025 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
A36 daysB88 daysC94 daysDNone of theseA contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b. 114 c. 134 d. 112
A1 dayB1 1/4 daysC1 3/4 daysD1 1/2 days
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant
View SolutionA contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. 1 b. 114 c. 134 d. 112
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View Solution