A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Understand the total work and the work done
The contractor employed 30 men to complete the project in 100 days. This means that the total work can be expressed in terms of man-days:
Total Work=Number of Men×Number of Days=30 men×100 days=3000 man-days

Step 2: Calculate the work done in 25 days
After 25 days, only 20% of the work is completed. Therefore, we can calculate the amount of work done:
Work Done=20% of Total Work=0.20×3000 man-days=600 man-days

Step 3: Calculate the remaining work
Now, we need to find out how much work is left to be completed:
Remaining Work=Total WorkWork Done=3000 man-days600 man-days=2400 man-days

Step 4: Determine how many days are needed to complete the remaining work
The contractor still has 30 men working on the project. We can find out how many additional days (let's call it X) are required to complete the remaining work:
Remaining Work=Number of Men×Number of Days
2400 man-days=30 men×X days
Solving for X:
X=2400 man-days30 men=80 days

Step 5: Calculate the total time taken
The total time taken to complete the project will be the initial 25 days plus the additional 80 days:
Total Time=25 days+80 days=105 days

Step 6: Calculate the extra days required
The extra days required beyond the scheduled time of 100 days is:
Extra Days=Total TimeScheduled Time=105 days100 days=5 days

Final Answer
The contractor will require an additional 5 days beyond the scheduled time.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?

    A15
    B20
    C25
    D30
  • 25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?

    A36 days
    B88 days
    C94 days
    DNone of these
  • A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b.  114 c. 134 d. 112

    A1 day
    B1 1/4 days
    C1 3/4 days
    D1 1/2 days