A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?
Step by step video & image solution for A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
Knowledge Check
- Question 1 - Select One
A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
A15B20C25D30 - Question 1 - Select One
25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
A36 daysB88 daysC94 daysDNone of these - Question 1 - Select One
A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b. 114 c. 134 d. 112
A1 dayB1 1/4 daysC1 3/4 daysD1 1/2 days - Question 1 - Select One
A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
Aa) 25Bb) 30Cc) 35Dd) 20 - Question 1 - Select One
20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
A10B12C15D20 - Question 1 - Select One
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant
View SolutionA contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. 1 b. 114 c. 134 d. 112
View Solution