Doubtnut Promotions Sticky

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?

Video Solution
|
Answer

Step by step video & image solution for A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?

    A15
    B20
    C25
    D30
  • Question 2 - Select One

    25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?

    A36 days
    B88 days
    C94 days
    DNone of these
  • Question 3 - Select One

    A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b.  114 c. 134 d. 112

    A1 day
    B1 1/4 days
    C1 3/4 days
    D1 1/2 days