A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the Total Work
The contractor initially employed 30 men to complete the project in 100 days. Therefore, the total amount of work can be calculated as:
Total Work=Number of Men×Days=30 men×100 days=3000 man-days

Hint: Total work can be calculated by multiplying the number of workers by the number of days they are supposed to work.

Step 2: Calculate Work Done in 25 Days
In the first 25 days, only 20% of the work was completed. Thus, the work done is:
Work Done=20% of Total Work=0.2×3000=600 man-days

Hint: To find the work done, multiply the total work by the percentage completed.

Step 3: Calculate Remaining Work
The remaining work after 25 days is:
Remaining Work=Total WorkWork Done=3000600=2400 man-days

Hint: Remaining work is simply the total work minus the work already completed.

Step 4: Determine Remaining Days
The total project duration is 100 days, and 25 days have already passed. Therefore, the remaining days are:
Remaining Days=10025=75 days

Hint: To find the remaining time, subtract the time already spent from the total time allotted.

Step 5: Calculate Required Men to Complete Remaining Work
To find out how many men are needed to complete the remaining work in the remaining days, we can use the formula:
Required Men=Remaining WorkRemaining Days=240075=32 men

Hint: The number of men required can be found by dividing the remaining work by the remaining days.

Step 6: Calculate Additional Men Needed
Initially, there were 30 men working. Now, we need 32 men to complete the work on time. Therefore, the additional number of men required is:
Additional Men=Required MenInitial Men=3230=2 men

Hint: To find out how many extra men are needed, subtract the initial number of men from the required number of men.

Final Answer
The contractor needs to increase the workforce by 2 men to complete the project on time.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

    A25
    B50
    C75
    Dcan't be determined
  • A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?

    A15
    B20
    C25
    D30
  • A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

    A50
    B40
    C30
    D10