A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the Total Work
The contractor initially employed 30 men to complete the project in 100 days. Therefore, the total amount of work can be calculated as:
Total Work=Number of Men×Days=30 men×100 days=3000 man-days
Hint: Total work can be calculated by multiplying the number of workers by the number of days they are supposed to work.
Step 2: Calculate Work Done in 25 Days
In the first 25 days, only 20% of the work was completed. Thus, the work done is:
Work Done=20% of Total Work=0.2×3000=600 man-days
Hint: To find the work done, multiply the total work by the percentage completed.
Step 3: Calculate Remaining Work
The remaining work after 25 days is:
Remaining Work=Total Work−Work Done=3000−600=2400 man-days
Hint: Remaining work is simply the total work minus the work already completed.
Step 4: Determine Remaining Days
The total project duration is 100 days, and 25 days have already passed. Therefore, the remaining days are:
Remaining Days=100−25=75 days
Hint: To find the remaining time, subtract the time already spent from the total time allotted.
Step 5: Calculate Required Men to Complete Remaining Work
To find out how many men are needed to complete the remaining work in the remaining days, we can use the formula:
Required Men=Remaining WorkRemaining Days=240075=32 men
Hint: The number of men required can be found by dividing the remaining work by the remaining days.
Step 6: Calculate Additional Men Needed
Initially, there were 30 men working. Now, we need 32 men to complete the work on time. Therefore, the additional number of men required is:
Additional Men=Required Men−Initial Men=32−30=2 men
Hint: To find out how many extra men are needed, subtract the initial number of men from the required number of men.
Final Answer
The contractor needs to increase the workforce by 2 men to complete the project on time.
---
The contractor initially employed 30 men to complete the project in 100 days. Therefore, the total amount of work can be calculated as:
Total Work=Number of Men×Days=30 men×100 days=3000 man-days
In the first 25 days, only 20% of the work was completed. Thus, the work done is:
Work Done=20% of Total Work=0.2×3000=600 man-days
The remaining work after 25 days is:
Remaining Work=Total Work−Work Done=3000−600=2400 man-days
The total project duration is 100 days, and 25 days have already passed. Therefore, the remaining days are:
Remaining Days=100−25=75 days
To find out how many men are needed to complete the remaining work in the remaining days, we can use the formula:
Required Men=Remaining WorkRemaining Days=240075=32 men
Initially, there were 30 men working. Now, we need 32 men to complete the work on time. Therefore, the additional number of men required is:
Additional Men=Required Men−Initial Men=32−30=2 men
The contractor needs to increase the workforce by 2 men to complete the project on time.
Topper's Solved these Questions
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View Solution
Knowledge Check
A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
A25B50C75Dcan't be determinedA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
A15B20C25D30A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
A50B40C30D10
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution