Doubtnut Promotions Sticky

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

    A25
    B50
    C75
    Dcan't be determined
  • Question 1 - Select One

    A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?

    A15
    B20
    C25
    D30
  • Question 1 - Select One

    A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

    A50
    B40
    C30
    D10
  • Question 1 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?

    A1. 4 days
    B2. 5 days
    C3. 8 days
    D4. 7 days
  • Question 1 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

    A5
    B6
    C3
    D9
  • Question 1 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45
  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32

Similar Questions