A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
1. 4 days
2. 5 days
3. 8 days
4. 7 days
The correct Answer is:B
Topper's Solved these Questions
Similar Questions
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b. 6 c. 7 d. 8
View SolutionA builder decided to build a farmhouse in 45 days. He employed 150 men in the beginning and120 more after 30 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
View Solution
Knowledge Check
- Question 1 - Select One
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
A5B6C3D9 - Question 2 - Select One
A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?
A5 daysB6 daysC8 daysD10 days - Question 3 - Select One
A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
A8B6C5D12
72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?
View SolutionIf 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?
View SolutionA contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution