A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?

A

1. 4 days

B

2. 5 days

C

3. 8 days

D

4. 7 days

Text Solution
Verified by Experts

The correct Answer is:B

Updated on:21/07/2023
Doubtnut Promotions Banner
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

    A5
    B6
    C3
    D9
  • A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?

    A5 days
    B6 days
    C8 days
    D10 days
  • A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

    A8
    B6
    C5
    D12