Doubtnut Promotions Sticky

33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?

A

21

B

42

C

45

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to determine how many days it will take for 44 men to complete a job if one man leaves at the end of each day.

Step 1: Calculate the total work
We know that 33 men can complete the work in 30 days. Therefore, the total work can be calculated as follows:

Total Work=Number of Men×Number of Days=33×30=990 man-days

Step 2: Determine the daily work done by 44 men
On the first day, 44 men will work together. Thus, the work done on the first day is:

Work done on Day 1=44 units

Step 3: Calculate the work done on subsequent days
Since one man leaves at the end of each day, the number of men working each day decreases by 1. Therefore, the work done on each subsequent day will be as follows:

- Day 1: 44 men → 44 units
- Day 2: 43 men → 43 units
- Day 3: 42 men → 42 units
- ...
- Day N: (44(N1)) men → (44(N1)) units

Step 4: Set up the equation for total work
The total work done over N days can be expressed as the sum of an arithmetic series:

Total Work=44+43+42++(44(N1))

This can be simplified using the formula for the sum of an arithmetic series:

Sum=N2×(First Term+Last Term)

Where:
- First Term = 44
- Last Term = 44(N1)=45N

Thus, the equation becomes:

Total Work=N2×(44+(45N))=N2×(89N)

Step 5: Set the equation equal to total work and solve for N
We know the total work is 990 units:

N2×(89N)=990

Multiplying both sides by 2 to eliminate the fraction:

N(89N)=1980

Rearranging gives us a quadratic equation:

N289N+1980=0

Step 6: Solve the quadratic equation
Using the quadratic formula N=b±b24ac2a:

Here, a=1,b=89,c=1980:

N=89±(89)24×1×19802×1

Calculating the discriminant:

(89)2=7921
4×1×1980=7920
79217920=1=1

Thus, substituting back into the formula:

N=89±12

Calculating the two possible values for N:

1. N=902=45
2. N=882=44

Since we need the minimum number of days, we take N=45.

Conclusion
The minimum number of days required to complete the whole work is 45 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?

    A36 days
    B88 days
    C94 days
    DNone of these
  • Question 2 - Select One

    If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.

    A130
    B1900
    C190
    D160
  • Question 3 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men