33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?
21
42
45
none of these
The correct Answer is:D
To solve the problem step by step, we need to determine how many days it will take for 44 men to complete a job if one man leaves at the end of each day.
Step 1: Calculate the total work
We know that 33 men can complete the work in 30 days. Therefore, the total work can be calculated as follows:
Total Work=Number of Men×Number of Days=33×30=990 man-days
Step 2: Determine the daily work done by 44 men
On the first day, 44 men will work together. Thus, the work done on the first day is:
Work done on Day 1=44 units
Step 3: Calculate the work done on subsequent days
Since one man leaves at the end of each day, the number of men working each day decreases by 1. Therefore, the work done on each subsequent day will be as follows:
- Day 1: 44 men → 44 units
- Day 2: 43 men → 43 units
- Day 3: 42 men → 42 units
- ...
- Day N: (44−(N−1)) men → (44−(N−1)) units
Step 4: Set up the equation for total work
The total work done over N days can be expressed as the sum of an arithmetic series:
Total Work=44+43+42+…+(44−(N−1))
This can be simplified using the formula for the sum of an arithmetic series:
Sum=N2×(First Term+Last Term)
Where:
- First Term = 44
- Last Term = 44−(N−1)=45−N
Thus, the equation becomes:
Total Work=N2×(44+(45−N))=N2×(89−N)
Step 5: Set the equation equal to total work and solve for N
We know the total work is 990 units:
N2×(89−N)=990
Multiplying both sides by 2 to eliminate the fraction:
N(89−N)=1980
Rearranging gives us a quadratic equation:
N2−89N+1980=0
Step 6: Solve the quadratic equation
Using the quadratic formula N=−b±√b2−4ac2a:
Here, a=1,b=−89,c=1980:
N=89±√(−89)2−4×1×19802×1
Calculating the discriminant:
(−89)2=7921
4×1×1980=7920
√7921−7920=√1=1
Thus, substituting back into the formula:
N=89±12
Calculating the two possible values for N:
1. N=902=45
2. N=882=44
Since we need the minimum number of days, we take N=45.
Conclusion
The minimum number of days required to complete the whole work is 45 days.
We know that 33 men can complete the work in 30 days. Therefore, the total work can be calculated as follows:
On the first day, 44 men will work together. Thus, the work done on the first day is:
Since one man leaves at the end of each day, the number of men working each day decreases by 1. Therefore, the work done on each subsequent day will be as follows:
- Day 2: 43 men → 43 units
- Day 3: 42 men → 42 units
- ...
- Day N: (44−(N−1)) men → (44−(N−1)) units
The total work done over N days can be expressed as the sum of an arithmetic series:
- First Term = 44
- Last Term = 44−(N−1)=45−N
We know the total work is 990 units:
Using the quadratic formula N=−b±√b2−4ac2a:
4×1×1980=7920
√7921−7920=√1=1
2. N=882=44
The minimum number of days required to complete the whole work is 45 days.
Topper's Solved these Questions
Similar Questions
If 5 men can do a piece of work in 10 days and 12 women can do the same work in 15 days, the number of days required to complete the work by 5 men and 6 women is
View SolutionA and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is
View Solution
Knowledge Check
- Question 1 - Select One
25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
A36 daysB88 daysC94 daysDNone of these - Question 2 - Select One
If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.
A130B1900C190D160 - Question 3 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 men
12 men finished 14th part of whole work in 6 days. Find the number of additional men required to complete the job innext 6 days.
View Solution6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View SolutionA and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
View Solution