Some-time after the new workers were introduced, all of the newly introduced workers left the work due to heavy rain and the efficiency of the remaining workers reduced by 20% due to which the work finally got completed by delay of 60% of the scheduled time then how much work still remained incomplete by the end of the scheduled time?
1735%
21%
2757%
28%
The correct Answer is:C
To solve the problem step by step, we will analyze the situation and calculate the amount of work that remains incomplete by the end of the scheduled time.
Step 1: Define Variables
Let:
- M = number of original workers
- X = number of newly introduced workers
- T = scheduled time to complete the work
Step 2: Calculate Total Work
The total work done by all workers together in scheduled time T is:
Total Work=(M+X)×T
Step 3: Calculate Efficiency After New Workers Leave
After the new workers leave, the efficiency of the remaining workers reduces by 20%. Therefore, the efficiency of the remaining workers becomes:
Remaining Efficiency=80% of (M+X)=0.8(M+X)
Step 4: Calculate Delayed Time
The work is completed with a delay of 60% of the scheduled time. Therefore, the actual time taken to complete the work is:
Actual Time=T+0.6T=1.6T
Step 5: Calculate Work Done in Actual Time
The work done by the remaining workers in the actual time is:
Work Done=Remaining Efficiency×Actual Time=0.8(M+X)×1.6T=1.28(M+X)T
Step 6: Set Up the Equation
Now, we can set up the equation based on the total work and the work done:
1.28(M+X)T=(M+X)T
This indicates that the total work done in the actual time is less than the total work required.
Step 7: Calculate Work Remaining
The remaining work can be calculated as:
Remaining Work=Total Work−Work Done=(M+X)T−1.28(M+X)T
=(1−1.28)(M+X)T=−0.28(M+X)T
Step 8: Calculate Percentage of Incomplete Work
To find out how much work remains incomplete by the end of the scheduled time, we can express this as a percentage of the total work:
Percentage of Incomplete Work=(−0.28(M+X)T(M+X)T)×100=−28%
Conclusion
Since the negative percentage indicates that the work was not completed as planned, we can conclude that 28% of the work remains incomplete by the end of the scheduled time.
Let:
- M = number of original workers
- X = number of newly introduced workers
- T = scheduled time to complete the work
The total work done by all workers together in scheduled time T is:
Total Work=(M+X)×T
After the new workers leave, the efficiency of the remaining workers reduces by 20%. Therefore, the efficiency of the remaining workers becomes:
Remaining Efficiency=80% of (M+X)=0.8(M+X)
The work is completed with a delay of 60% of the scheduled time. Therefore, the actual time taken to complete the work is:
Actual Time=T+0.6T=1.6T
The work done by the remaining workers in the actual time is:
Work Done=Remaining Efficiency×Actual Time=0.8(M+X)×1.6T=1.28(M+X)T
Now, we can set up the equation based on the total work and the work done:
1.28(M+X)T=(M+X)T
This indicates that the total work done in the actual time is less than the total work required.
The remaining work can be calculated as:
Remaining Work=Total Work−Work Done=(M+X)T−1.28(M+X)T
=(1−1.28)(M+X)T=−0.28(M+X)T
To find out how much work remains incomplete by the end of the scheduled time, we can express this as a percentage of the total work:
Percentage of Incomplete Work=(−0.28(M+X)T(M+X)T)×100=−28%
Since the negative percentage indicates that the work was not completed as planned, we can conclude that 28% of the work remains incomplete by the end of the scheduled time.
Topper's Solved these Questions
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View Solution
Knowledge Check
- Question 1 - Select One
Henry and Ford are two different persons, but when they work together, they complete it in 10 days. Had Henry worked at half of his efficient and Ford at five times of his efficiency it would have taken them to finish the job in 50% of the scheduled time. In how many days can Ford complete the job working alone?
A12B25C15D30 - Question 2 - Select One
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
A16B15C20D25 - Question 3 - Select One
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
A60B80C20D25
6400 workers were employed to construct a factory in 4 years. A the end of the first year, 25% workers were retrenched. At the end of the second year, 25% of those working at that time were again retrenched. However, to complete the project in time, the number of workers was increased by 25% of the total number of workers left at the end of third year. How many workers were working during the fourth year ?
View SolutionHenry and Ford are two different persons, but when they work together, they complete it in 10 days. Had Henry worked at half of his efficient and Ford at five times of his efficiency it would have taken them to finish the job in 50% of the scheduled time. In how many days can Ford complete the job working alone?
View SolutionBoston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?
View SolutionBoston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?
View Solution16 days after the 20% typist left the job it was decided to complete the work on time by increasing the work-force again. By how much percentage increase in work-force is requried?
View Solution