Doubtnut Promotions Sticky

Some-time after the new workers were introduced, all of the newly introduced workers left the work due to heavy rain and the efficiency of the remaining workers reduced by 20% due to which the work finally got completed by delay of 60% of the scheduled time then how much work still remained incomplete by the end of the scheduled time?

A

1735%

B

21%

C

2757%

D

28%

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will analyze the situation and calculate the amount of work that remains incomplete by the end of the scheduled time.

Step 1: Define Variables
Let:
- M = number of original workers
- X = number of newly introduced workers
- T = scheduled time to complete the work

Step 2: Calculate Total Work
The total work done by all workers together in scheduled time T is:
Total Work=(M+X)×T

Step 3: Calculate Efficiency After New Workers Leave
After the new workers leave, the efficiency of the remaining workers reduces by 20%. Therefore, the efficiency of the remaining workers becomes:
Remaining Efficiency=80% of (M+X)=0.8(M+X)

Step 4: Calculate Delayed Time
The work is completed with a delay of 60% of the scheduled time. Therefore, the actual time taken to complete the work is:
Actual Time=T+0.6T=1.6T

Step 5: Calculate Work Done in Actual Time
The work done by the remaining workers in the actual time is:
Work Done=Remaining Efficiency×Actual Time=0.8(M+X)×1.6T=1.28(M+X)T

Step 6: Set Up the Equation
Now, we can set up the equation based on the total work and the work done:
1.28(M+X)T=(M+X)T
This indicates that the total work done in the actual time is less than the total work required.

Step 7: Calculate Work Remaining
The remaining work can be calculated as:
Remaining Work=Total WorkWork Done=(M+X)T1.28(M+X)T
=(11.28)(M+X)T=0.28(M+X)T

Step 8: Calculate Percentage of Incomplete Work
To find out how much work remains incomplete by the end of the scheduled time, we can express this as a percentage of the total work:
Percentage of Incomplete Work=(0.28(M+X)T(M+X)T)×100=28%

Conclusion
Since the negative percentage indicates that the work was not completed as planned, we can conclude that 28% of the work remains incomplete by the end of the scheduled time.

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Henry and Ford are two different persons, but when they work together, they complete it in 10 days. Had Henry worked at half of his efficient and Ford at five times of his efficiency it would have taken them to finish the job in 50% of the scheduled time. In how many days can Ford complete the job working alone?

    A12
    B25
    C15
    D30
  • Question 2 - Select One

    A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

    A16
    B15
    C20
    D25
  • Question 3 - Select One

    A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?

    A60
    B80
    C20
    D25