A, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?
The correct Answer is:7 days
To solve the problem, we need to determine how long it will take A, B, and C to complete the work together, considering the conditions given in the question.
1. Calculate the Work Rates of A, B, and C:
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 12 days, so B's work rate is 112 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.
2. Find the Combined Work Rate:
- To find the combined work rate of A, B, and C working together, we add their individual work rates:
Combined work rate=110+112+115
- To add these fractions, we need a common denominator. The LCM of 10, 12, and 15 is 60.
- Converting each fraction:
110=660,112=560,115=460
- Now, adding them:
Combined work rate=660+560+460=1560=14
- This means together they can complete 14 of the work in one day.
3. Determine the Total Work:
- The total work can be considered as 1 unit of work.
4. Calculate the Time Taken to Complete the Work:
- Let T be the total time taken to complete the work.
- Since A leaves 5 days before completion and B leaves 2 days after A, we can break down the work:
- Let T−5 be the time A worked (A works for T−5 days).
- B works for T−2 days (B works for 2 days longer than A).
- C works for the entire T days.
5. Set Up the Equation:
- The work done by A, B, and C can be expressed as:
Work done by A=110(T−5)
Work done by B=112(T−2)
Work done by C=115(T)
- The total work done by A, B, and C together should equal 1:
110(T−5)+112(T−2)+115(T)=1
6. Solve the Equation:
- Multiply through by 60 (the LCM of 10, 12, and 15) to eliminate the denominators:
6(T−5)+5(T−2)+4T=60
- Expanding this gives:
6T−30+5T−10+4T=60
- Combine like terms:
15T−40=60
- Add 40 to both sides:
15T=100
- Divide by 15:
T=10015=203≈6.67 days
Final Answer:
The total time taken to complete the work is approximately 6.67 days.
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 12 days, so B's work rate is 112 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.
- To find the combined work rate of A, B, and C working together, we add their individual work rates:
Combined work rate=110+112+115
- To add these fractions, we need a common denominator. The LCM of 10, 12, and 15 is 60.
- Converting each fraction:
110=660,112=560,115=460
- Now, adding them:
Combined work rate=660+560+460=1560=14
- This means together they can complete 14 of the work in one day.
- The total work can be considered as 1 unit of work.
- Let T be the total time taken to complete the work.
- Since A leaves 5 days before completion and B leaves 2 days after A, we can break down the work:
- Let T−5 be the time A worked (A works for T−5 days).
- B works for T−2 days (B works for 2 days longer than A).
- C works for the entire T days.
- The work done by A, B, and C can be expressed as:
Work done by A=110(T−5)
Work done by B=112(T−2)
Work done by C=115(T)
- The total work done by A, B, and C together should equal 1:
110(T−5)+112(T−2)+115(T)=1
- Multiply through by 60 (the LCM of 10, 12, and 15) to eliminate the denominators:
6(T−5)+5(T−2)+4T=60
- Expanding this gives:
6T−30+5T−10+4T=60
- Combine like terms:
15T−40=60
- Add 40 to both sides:
15T=100
- Divide by 15:
T=10015=203≈6.67 days
The total time taken to complete the work is approximately 6.67 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a work in 25, 40 and 60 days respectively. All three start the work together and work for 5 days then A left and B left 10 days before the completion of work, how much time shall be taken to do whole work?
View SolutionA and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these - Question 2 - Select One
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these - Question 3 - Select One
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View Solution