Doubtnut Promotions Sticky

A, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:7 days


To solve the problem, we need to determine how long it will take A, B, and C to complete the work together, considering the conditions given in the question.

1. Calculate the Work Rates of A, B, and C:
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 12 days, so B's work rate is 112 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.

2. Find the Combined Work Rate:
- To find the combined work rate of A, B, and C working together, we add their individual work rates:
Combined work rate=110+112+115
- To add these fractions, we need a common denominator. The LCM of 10, 12, and 15 is 60.
- Converting each fraction:
110=660,112=560,115=460
- Now, adding them:
Combined work rate=660+560+460=1560=14
- This means together they can complete 14 of the work in one day.

3. Determine the Total Work:
- The total work can be considered as 1 unit of work.

4. Calculate the Time Taken to Complete the Work:
- Let T be the total time taken to complete the work.
- Since A leaves 5 days before completion and B leaves 2 days after A, we can break down the work:
- Let T5 be the time A worked (A works for T5 days).
- B works for T2 days (B works for 2 days longer than A).
- C works for the entire T days.

5. Set Up the Equation:
- The work done by A, B, and C can be expressed as:
Work done by A=110(T5)
Work done by B=112(T2)
Work done by C=115(T)
- The total work done by A, B, and C together should equal 1:
110(T5)+112(T2)+115(T)=1

6. Solve the Equation:
- Multiply through by 60 (the LCM of 10, 12, and 15) to eliminate the denominators:
6(T5)+5(T2)+4T=60
- Expanding this gives:
6T30+5T10+4T=60
- Combine like terms:
15T40=60
- Add 40 to both sides:
15T=100
- Divide by 15:
T=10015=2036.67 days

Final Answer:
The total time taken to complete the work is approximately 6.67 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 2 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A13
    B12
    C14
    D11