A and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work?
The correct Answer is:24 days
Step by step video, text & image solution for A and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
A, B and C can do a work in 25, 40 and 60 days respectively. All three start the work together and work for 5 days then A left and B left 10 days before the completion of work, how much time shall be taken to do whole work?
View SolutionA, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
A30B27C25D24 - Question 2 - Select One or More
A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
A24B18C36D42 - Question 3 - Select One
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
A10 daysB8 daysC12 daysD15 days
A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionP can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
View SolutionA and B can do a work in 6 days and 8 days respectively. Together they worked for 3 days and left. C complete the remaining work in 2 days. Find in how many days B and C together can complete 3/4th part of the total work.
View SolutionA and B can do a piece of work in 24 and 30 days respectively.
Both started the work and worked for 6 days. Then B leaves
the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
alone can do the workView Solution