Doubtnut Promotions Sticky

A, B and C can do a work in 25, 40 and 60 days respectively. All three start the work together and work for 5 days then A left and B left 10 days before the completion of work, how much time shall be taken to do whole work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:2515 days


To solve the problem step by step, we will first calculate the work done by A, B, and C, and then determine how long it takes to complete the entire work.

Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 25 days, so A's work rate is 125 of the work per day.
- B can complete the work in 40 days, so B's work rate is 140 of the work per day.
- C can complete the work in 60 days, so C's work rate is 160 of the work per day.

Step 2: Find the combined work rate of A, B, and C.
To find the combined work rate, we add their individual work rates:
Combined work rate=125+140+160

To add these fractions, we need to find a common denominator. The LCM of 25, 40, and 60 is 600.

Calculating each work rate:
- 125=24600
- 140=15600
- 160=10600

Now, adding them together:
Combined work rate=24+15+10600=49600

Step 3: Calculate the work done in the first 5 days.
In 5 days, the amount of work done by A, B, and C together is:
Work done in 5 days=5×49600=245600

Step 4: Determine the remaining work.
The total work is considered as 1 (or 600 units). The remaining work after 5 days is:
Remaining work=1245600=355600

Step 5: Determine when B leaves the work.
Let x be the total number of days taken to complete the work. B leaves 10 days before the work is completed, which means B works for x10 days.

Step 6: Calculate the work done by B and C after A leaves.
After 5 days, A leaves, and B and C continue working. Their combined work rate is:
B's work rate+C's work rate=140+160

Finding a common denominator (LCM of 40 and 60 is 120):
- 140=3120
- 160=2120

Adding them together:
B + C work rate=3+2120=5120=124

Step 7: Calculate the work done by B and C.
Let y be the number of days B and C work together after A leaves. Thus:
y=x510=x15
The work done by B and C together is:
Work done by B and C=(x15)×124

Step 8: Set up the equation for total work.
The total work done can be expressed as:
245600+(x15)×124=1

Step 9: Solve for x.
Rearranging the equation:
(x15)×124=1245600
Calculating the right side:
1245600=600245600=355600
Thus:
(x15)×124=355600
Multiplying both sides by 24:
x15=355×24600
Calculating the right side:
355×24600=8520600=14.2
Thus:
x15=14.2x=29.2

Step 10: Finalize the total time taken.
Since we are looking for the total time taken, we round x to the nearest whole number:
Total time taken=29.2 days30 days

Final Answer:
The total time taken to complete the work is approximately 30 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • Question 2 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these