A can finish 25 of work done by B in 14 of time taken by B. B can finish 43 of work done by C in 35 of time taken by C. Working together they can finish the work in 60 days. In how many days they will finish the work, working alone?
The correct Answer is:11438 days, 183 days, 40623 days
To solve the problem step by step, we will analyze the work done by A, B, and C based on the information provided.
Step 1: Establish the relationships between A, B, and C
1. A's work in relation to B:
- A can finish 25 of the work done by B in 14 of the time taken by B.
- Let's assume B takes t days to complete the work. Then A takes t4 days to do 25 of B's work.
- Therefore, in one day, A does:
Work done by A in one day=2/5t/4=2×45×t=85t
- In one day, B does:
Work done by B in one day=1t
2. Efficiency Ratio of A to B:
- The efficiency ratio of A to B is:
Efficiency of A:Efficiency of B=85t:1t=8:5
Step 2: Establish the relationship between B and C
1. B's work in relation to C:
- B can finish 43 of the work done by C in 35 of the time taken by C.
- Let C take s days to complete the work. Then B takes 3s5 days to do 43 of C's work.
- Therefore, in one day, C does:
Work done by C in one day=1s
- In one day, B does:
Work done by B in one day=4/33s/5=4×53×3s=209s
2. Efficiency Ratio of B to C:
- The efficiency ratio of B to C is:
Efficiency of B:Efficiency of C=209s:1s=20:9
Step 3: Combine the ratios
1. Combine A, B, and C's efficiencies:
- We have:
- A:B=8:5
- B:C=20:9
- To combine these ratios, we need to make the B parts equal. We can multiply the first ratio by 4:
A:B=32:20
- Now we can write:
A:B:C=32:20:9
Step 4: Calculate the total efficiency
1. Total efficiency:
- Total efficiency = 32+20+9=61
Step 5: Calculate total work done
1. Work done together in 60 days:
- If they can finish the work together in 60 days, then the total work is:
Total Work=Total Efficiency×Time=61×60=3660 units
Step 6: Calculate individual work done by A, B, and C
1. Work done by A in one day:
- A's efficiency = 32 units/day
- Days taken by A to finish the work:
Days taken by A=366032=114.375 days
2. Work done by B in one day:
- B's efficiency = 20 units/day
- Days taken by B to finish the work:
Days taken by B=366020=183 days
3. Work done by C in one day:
- C's efficiency = 9 units/day
- Days taken by C to finish the work:
Days taken by C=36609=406.67 days
Final Answer
- A can finish the work alone in 114.375 days.
- B can finish the work alone in 183 days.
- C can finish the work alone in 406.67 days.
- A can finish 25 of the work done by B in 14 of the time taken by B.
- Let's assume B takes t days to complete the work. Then A takes t4 days to do 25 of B's work.
- Therefore, in one day, A does:
Work done by A in one day=2/5t/4=2×45×t=85t
- In one day, B does:
Work done by B in one day=1t
- The efficiency ratio of A to B is:
Efficiency of A:Efficiency of B=85t:1t=8:5
- B can finish 43 of the work done by C in 35 of the time taken by C.
- Let C take s days to complete the work. Then B takes 3s5 days to do 43 of C's work.
- Therefore, in one day, C does:
Work done by C in one day=1s
- In one day, B does:
Work done by B in one day=4/33s/5=4×53×3s=209s
- The efficiency ratio of B to C is:
Efficiency of B:Efficiency of C=209s:1s=20:9
- We have:
- A:B=8:5
- B:C=20:9
- To combine these ratios, we need to make the B parts equal. We can multiply the first ratio by 4:
A:B=32:20
- Now we can write:
A:B:C=32:20:9
- Total efficiency = 32+20+9=61
- If they can finish the work together in 60 days, then the total work is:
Total Work=Total Efficiency×Time=61×60=3660 units
- A's efficiency = 32 units/day
- Days taken by A to finish the work:
Days taken by A=366032=114.375 days
- B's efficiency = 20 units/day
- Days taken by B to finish the work:
Days taken by B=366020=183 days
- C's efficiency = 9 units/day
- Days taken by C to finish the work:
Days taken by C=36609=406.67 days
- A can finish the work alone in 114.375 days.
- B can finish the work alone in 183 days.
- C can finish the work alone in 406.67 days.
Topper's Solved these Questions
Similar Questions
A can finish 80% of work done by B in 20% more time taken by B. Working together they can finish the work in 40 days. In how many days they will finish the work working alone?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
A10B21C12D11 - Question 2 - Select One
A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
A10B10.5C12D11 - Question 3 - Select One
A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
A18 daysB21 daysC24 daysD27 days
A is twice as good a work man as B together they finish a piece of work in 18 days . In how many days will A alone finish the work ?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
View SolutionA and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?
View Solution