Doubtnut Promotions Sticky

A can finish 25 of work done by B in 14 of time taken by B. B can finish 43 of work done by C in 35 of time taken by C. Working together they can finish the work in 60 days. In how many days they will finish the work, working alone?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:11438 days, 183 days, 40623 days


To solve the problem step by step, we will analyze the work done by A, B, and C based on the information provided.

Step 1: Establish the relationships between A, B, and C

1. A's work in relation to B:
- A can finish 25 of the work done by B in 14 of the time taken by B.
- Let's assume B takes t days to complete the work. Then A takes t4 days to do 25 of B's work.
- Therefore, in one day, A does:
Work done by A in one day=2/5t/4=2×45×t=85t
- In one day, B does:
Work done by B in one day=1t

2. Efficiency Ratio of A to B:
- The efficiency ratio of A to B is:
Efficiency of A:Efficiency of B=85t:1t=8:5

Step 2: Establish the relationship between B and C

1. B's work in relation to C:
- B can finish 43 of the work done by C in 35 of the time taken by C.
- Let C take s days to complete the work. Then B takes 3s5 days to do 43 of C's work.
- Therefore, in one day, C does:
Work done by C in one day=1s
- In one day, B does:
Work done by B in one day=4/33s/5=4×53×3s=209s

2. Efficiency Ratio of B to C:
- The efficiency ratio of B to C is:
Efficiency of B:Efficiency of C=209s:1s=20:9

Step 3: Combine the ratios

1. Combine A, B, and C's efficiencies:
- We have:
- A:B=8:5
- B:C=20:9
- To combine these ratios, we need to make the B parts equal. We can multiply the first ratio by 4:
A:B=32:20
- Now we can write:
A:B:C=32:20:9

Step 4: Calculate the total efficiency

1. Total efficiency:
- Total efficiency = 32+20+9=61

Step 5: Calculate total work done

1. Work done together in 60 days:
- If they can finish the work together in 60 days, then the total work is:
Total Work=Total Efficiency×Time=61×60=3660 units

Step 6: Calculate individual work done by A, B, and C

1. Work done by A in one day:
- A's efficiency = 32 units/day
- Days taken by A to finish the work:
Days taken by A=366032=114.375 days

2. Work done by B in one day:
- B's efficiency = 20 units/day
- Days taken by B to finish the work:
Days taken by B=366020=183 days

3. Work done by C in one day:
- C's efficiency = 9 units/day
- Days taken by C to finish the work:
Days taken by C=36609=406.67 days

Final Answer
- A can finish the work alone in 114.375 days.
- B can finish the work alone in 183 days.
- C can finish the work alone in 406.67 days.

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?

    A10
    B21
    C12
    D11
  • Question 2 - Select One

    A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?

    A10
    B10.5
    C12
    D11
  • Question 3 - Select One

    A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?

    A18 days
    B21 days
    C24 days
    D27 days