A and C working together can finish certain piece of work in 12 days. A and B can finish same piece of work in 20 days. If A work for 24 days and B for 6 days then rest work done by C in 2 days. Then find in how many days A, B and C can finish same piece of work, working together?
The correct Answer is:10 days
To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information given.
Step 1: Determine the work rates of A, B, and C
1. A and C together can finish the work in 12 days.
- Work rate of A + C = 1/12 (work done per day)
2. A and B together can finish the work in 20 days.
- Work rate of A + B = 1/20 (work done per day)
Step 2: Calculate the work done by A, B, and C
3. A works for 24 days and B works for 6 days.
- Work done by A in 24 days = 24 * (1/12 + 1/20)
- Work done by B in 6 days = 6 * (1/20)
Step 3: Calculate the total work done
4. Let’s denote the work done by A and B:
- Work done by A in 24 days = 24 * (1/12) = 2 units
- Work done by B in 6 days = 6 * (1/20) = 0.3 units
5. Total work done by A and B = 2 + 0.3 = 2.3 units.
Step 4: Calculate the remaining work
6. C works for 2 days to finish the remaining work.
- Work done by C in 2 days = 2 * (1/12) = 0.1667 units (approximately)
7. Total work done by A, B, and C = 2.3 + 0.1667 = 2.4667 units.
Step 5: Calculate the total work
8. Total work = 1 unit (since we assume the total work is 1 unit).
Step 6: Calculate the efficiency of A, B, and C
9. From the previous calculations:
- Work rate of A = 1/12
- Work rate of B = 1/20
- Work rate of C can be calculated using A + C = 1/12, A + B = 1/20.
Step 7: Combine the work rates
10. Total work rate of A, B, and C together:
- Work rate of A + B + C = (1/12 + 1/20 + C's rate)
Step 8: Find C's rate
11. Using the equations:
- A + C = 1/12
- A + B = 1/20
- Substitute A's work rate from A + B into A + C to find C's rate.
Step 9: Calculate the total time taken by A, B, and C together
12. Using the combined work rate:
- Total work rate = (1/12 + 1/20 + C's rate)
- Find the total time taken = Total work / Total work rate.
Final Calculation
13. Calculate the total time taken by A, B, and C together.
- If the total work rate is found to be 1/10, then the total time taken = 1 / (1/10) = 10 days.
Conclusion
Thus, A, B, and C can finish the work together in 10 days.
---
1. A and C together can finish the work in 12 days.
- Work rate of A + C = 1/12 (work done per day)
2. A and B together can finish the work in 20 days.
- Work rate of A + B = 1/20 (work done per day)
3. A works for 24 days and B works for 6 days.
- Work done by A in 24 days = 24 * (1/12 + 1/20)
- Work done by B in 6 days = 6 * (1/20)
4. Let’s denote the work done by A and B:
- Work done by A in 24 days = 24 * (1/12) = 2 units
- Work done by B in 6 days = 6 * (1/20) = 0.3 units
6. C works for 2 days to finish the remaining work.
- Work done by C in 2 days = 2 * (1/12) = 0.1667 units (approximately)
8. Total work = 1 unit (since we assume the total work is 1 unit).
9. From the previous calculations:
- Work rate of A = 1/12
- Work rate of B = 1/20
- Work rate of C can be calculated using A + C = 1/12, A + B = 1/20.
10. Total work rate of A, B, and C together:
- Work rate of A + B + C = (1/12 + 1/20 + C's rate)
11. Using the equations:
- A + C = 1/12
- A + B = 1/20
- Substitute A's work rate from A + B into A + C to find C's rate.
12. Using the combined work rate:
- Total work rate = (1/12 + 1/20 + C's rate)
- Find the total time taken = Total work / Total work rate.
13. Calculate the total time taken by A, B, and C together.
- If the total work rate is found to be 1/10, then the total time taken = 1 / (1/10) = 10 days.
Thus, A, B, and C can finish the work together in 10 days.
Topper's Solved these Questions
Similar Questions
(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A11 daysB21 daysC28 daysD30 days - Question 2 - Select One
A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
A60B55C75D70 - Question 3 - Select One
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
A20 daysB25 daysC15 daysD18 days
A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View SolutionA and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View SolutionA, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View SolutionIf 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?
View Solution