Doubtnut Promotions Sticky

A and C working together can finish certain piece of work in 12 days. A and B can finish same piece of work in 20 days. If A work for 24 days and B for 6 days then rest work done by C in 2 days. Then find in how many days A, B and C can finish same piece of work, working together?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:10 days


To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information given.

Step 1: Determine the work rates of A, B, and C
1. A and C together can finish the work in 12 days.
- Work rate of A + C = 1/12 (work done per day)

2. A and B together can finish the work in 20 days.
- Work rate of A + B = 1/20 (work done per day)

Step 2: Calculate the work done by A, B, and C
3. A works for 24 days and B works for 6 days.
- Work done by A in 24 days = 24 * (1/12 + 1/20)
- Work done by B in 6 days = 6 * (1/20)

Step 3: Calculate the total work done
4. Let’s denote the work done by A and B:
- Work done by A in 24 days = 24 * (1/12) = 2 units
- Work done by B in 6 days = 6 * (1/20) = 0.3 units

5. Total work done by A and B = 2 + 0.3 = 2.3 units.

Step 4: Calculate the remaining work
6. C works for 2 days to finish the remaining work.
- Work done by C in 2 days = 2 * (1/12) = 0.1667 units (approximately)

7. Total work done by A, B, and C = 2.3 + 0.1667 = 2.4667 units.

Step 5: Calculate the total work
8. Total work = 1 unit (since we assume the total work is 1 unit).

Step 6: Calculate the efficiency of A, B, and C
9. From the previous calculations:
- Work rate of A = 1/12
- Work rate of B = 1/20
- Work rate of C can be calculated using A + C = 1/12, A + B = 1/20.

Step 7: Combine the work rates
10. Total work rate of A, B, and C together:
- Work rate of A + B + C = (1/12 + 1/20 + C's rate)

Step 8: Find C's rate
11. Using the equations:
- A + C = 1/12
- A + B = 1/20
- Substitute A's work rate from A + B into A + C to find C's rate.

Step 9: Calculate the total time taken by A, B, and C together
12. Using the combined work rate:
- Total work rate = (1/12 + 1/20 + C's rate)
- Find the total time taken = Total work / Total work rate.

Final Calculation
13. Calculate the total time taken by A, B, and C together.
- If the total work rate is found to be 1/10, then the total time taken = 1 / (1/10) = 10 days.

Conclusion
Thus, A, B, and C can finish the work together in 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

    A11 days
    B21 days
    C28 days
    D30 days
  • Question 2 - Select One

    A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?

    A60
    B55
    C75
    D70
  • Question 3 - Select One

    A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A20 days
    B25 days
    C15 days
    D18 days