A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
20
25
30
35
The correct Answer is:30
To solve the problem, we will follow these steps:
Step 1: Define Variables
Let the original number of men be x.
Step 2: Set Up the Work Equation
According to the problem, the group of men decided to complete the work in 10 days. Therefore, the total work done can be represented as:
Total Work=Number of Men×Days=x×10=10x
Step 3: Adjust for Absentees
When 5 men become absent, the number of men remaining is x−5. The remaining men complete the work in 12 days. Thus, the total work done by the remaining men can be represented as:
Total Work=Number of Remaining Men×Days=(x−5)×12
Step 4: Set the Two Work Equations Equal
Since the total work remains the same, we can set the two equations equal to each other:
10x=(x−5)×12
Step 5: Expand and Simplify the Equation
Expanding the right side gives:
10x=12x−60
Step 6: Rearrange the Equation
Rearranging the equation to isolate x:
10x−12x=−60
−2x=−60
2x=60
x=30
Step 7: Conclusion
The original number of men is x=30.
Thus, the answer is 30.
---
Let the original number of men be x.
According to the problem, the group of men decided to complete the work in 10 days. Therefore, the total work done can be represented as:
Total Work=Number of Men×Days=x×10=10x
When 5 men become absent, the number of men remaining is x−5. The remaining men complete the work in 12 days. Thus, the total work done by the remaining men can be represented as:
Total Work=Number of Remaining Men×Days=(x−5)×12
Since the total work remains the same, we can set the two equations equal to each other:
10x=(x−5)×12
Expanding the right side gives:
10x=12x−60
Rearranging the equation to isolate x:
10x−12x=−60
−2x=−60
2x=60
x=30
The original number of men is x=30.
Topper's Solved these Questions
Similar Questions
A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
View SolutionA contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed
View Solution
Knowledge Check
Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?
A10B21C15D18Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A24B20C16D18A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
AA) 8BB) 10CC) 12DD) 15
A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
View SolutionA contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .
View SolutionA group of persons can do a work in 10 days. If 5 persons remains absent from first day, then the work is completed in 12 days by remaining persons. Tell how many persons were in the group initially?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution