A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?

A

20

B

25

C

30

D

35

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:30


To solve the problem, we will follow these steps:

Step 1: Define Variables
Let the original number of men be x.

Step 2: Set Up the Work Equation
According to the problem, the group of men decided to complete the work in 10 days. Therefore, the total work done can be represented as:
Total Work=Number of Men×Days=x×10=10x

Step 3: Adjust for Absentees
When 5 men become absent, the number of men remaining is x5. The remaining men complete the work in 12 days. Thus, the total work done by the remaining men can be represented as:
Total Work=Number of Remaining Men×Days=(x5)×12

Step 4: Set the Two Work Equations Equal
Since the total work remains the same, we can set the two equations equal to each other:
10x=(x5)×12

Step 5: Expand and Simplify the Equation
Expanding the right side gives:
10x=12x60

Step 6: Rearrange the Equation
Rearranging the equation to isolate x:
10x12x=60
2x=60
2x=60
x=30

Step 7: Conclusion
The original number of men is x=30.

Thus, the answer is 30.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18
  • Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18
  • A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.

    AA) 8
    BB) 10
    CC) 12
    DD) 15