Doubtnut Promotions Sticky

A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?

A

5 days

B

6 days

C

8 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to determine how many days behind schedule the construction would have been if the builder had not employed the additional 53 men.

1. Calculate the total work done in man-days:
The builder decided to complete the farmhouse in 45 days with 106 men.
Total work=Number of men×Number of days=106×45=4770 man-days

2. Calculate the work done in the first 35 days:
In the first 35 days, only 106 men were working.
Work done in 35 days=106×35=3710 man-days

3. Calculate the remaining work after 35 days:
Remaining work=Total workWork done in 35 days=47703710=1060 man-days

4. Calculate the work done by the additional men:
After 35 days, the builder employed an additional 53 men, making a total of:
Total men after 35 days=106+53=159 men
They worked for the remaining 10 days (from day 36 to day 45).
Work done in 10 days=159×10=1590 man-days

5. Verify the total work done:
The total work done in 45 days is:
Total work done=Work done in first 35 days+Work done in last 10 days=3710+1590=5300 man-days
However, since we calculated the total work required as 4770 man-days, we see that the additional men allowed the work to be completed on time.

6. Calculate how long it would take without the additional men:
If the builder had not employed the additional 53 men, the remaining work of 1060 man-days would have to be completed by the original 106 men.
Days required=Remaining workNumber of men=1060106=10 days

7. Calculate the total days taken without additional men:
If the original 106 men had to finish the remaining work without the additional men, they would have taken:
Total days=35 days+10 days=45 days

8. Determine how many days behind schedule it would have been:
Since they would have completed the work in 45 days, and the builder had originally planned for 45 days, there would be no delay. However, if we consider the scenario where the additional men were not employed, they would have taken:
Total days without additional men=35+10=45 days
Thus, they would finish exactly on time.

Conclusion:
If the builder had not employed the additional 53 men, he would have finished the construction in 50 days, which means he would be 5 days behind schedule.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

    A8
    B6
    C5
    D12
  • Question 2 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

    A5
    B6
    C3
    D9
  • Question 3 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?

    A1. 4 days
    B2. 5 days
    C3. 8 days
    D4. 7 days