Doubtnut Promotions Sticky

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b.  6 c. 7 d. 8

Video Solution
|
Answer

Step by step video & image solution for A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b. \ 6 c. 7 d. 8 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b.  6 c. 7 d. 8

    A5
    B6
    C3
    D9
  • Question 2 - Select One

    A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?

    A1. 4 days
    B2. 5 days
    C3. 8 days
    D4. 7 days
  • Question 3 - Select One

    A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?

    A5 days
    B6 days
    C8 days
    D10 days