A builder decided to build a farmhouse in 45 days. He employed 150 men in the beginning and120 more after 30 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
The correct Answer is:12
To solve the problem step by step, we need to determine how many days behind schedule the construction would have been if the builder had not employed the additional men.
Step 1: Calculate the total work done in man-days.
The builder initially employed 150 men for 30 days. The total work done in this period can be calculated as:
Work=Number of men×Number of days=150×30=4500 man-days
Hint: Remember that man-days represent the total amount of work done, where one man working for one day counts as one man-day.
Step 2: Determine the remaining work after 30 days.
Since the builder completed the construction in 45 days, he had 15 days left after the first 30 days. The total work required to complete the farmhouse is equal to the work done in the first 30 days plus the work done in the next 15 days with the additional men.
Let’s denote the total work required to complete the farmhouse as W. The work done in the last 15 days with 270 men (150 original + 120 additional) is:
Work=270×15=4050 man-days
Thus, the total work W is:
W=4500+4050=8550 man-days
Hint: To find the total work, sum the work done in both phases of construction.
Step 3: Calculate how long it would take with only 150 men.
If only 150 men were employed for the entire duration, we need to find out how many days it would take to complete 8550 man-days of work:
Days=Total WorkNumber of men=8550150=57 days
Hint: When calculating the number of days, divide the total work by the number of workers to find out how many days it will take.
Step 4: Determine how many days behind schedule this would be.
The builder had originally planned to complete the farmhouse in 45 days. If it would take 57 days with only 150 men, we can find how many days behind schedule this is by subtracting the planned days from the actual days taken:
Days behind schedule=57−45=12 days
Hint: To find the delay, simply subtract the scheduled completion time from the actual completion time.
Final Answer:
The construction would have been finished 12 days behind schedule if the builder had not employed the additional men.
---
The builder initially employed 150 men for 30 days. The total work done in this period can be calculated as:
Work=Number of men×Number of days=150×30=4500 man-days
Since the builder completed the construction in 45 days, he had 15 days left after the first 30 days. The total work required to complete the farmhouse is equal to the work done in the first 30 days plus the work done in the next 15 days with the additional men.
Work=270×15=4050 man-days
W=4500+4050=8550 man-days
If only 150 men were employed for the entire duration, we need to find out how many days it would take to complete 8550 man-days of work:
Days=Total WorkNumber of men=8550150=57 days
The builder had originally planned to complete the farmhouse in 45 days. If it would take 57 days with only 150 men, we can find how many days behind schedule this is by subtracting the planned days from the actual days taken:
Days behind schedule=57−45=12 days
The construction would have been finished 12 days behind schedule if the builder had not employed the additional men.
Topper's Solved these Questions
Similar Questions
A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. 5 b. 6 c. 7 d. 8
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
View Solution
Knowledge Check
A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?
A8B6C5D12A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?
A5 daysB6 daysC8 daysD10 daysA contractor undertakes to do a piece of work in 40 days. He engages 100 men at eh beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional me, how many days behind the schedule the work should have been finished? 5 b. 6 c. 7 d. 8
A5B6C3D9
A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? 1 b. 114 c. 134 d. 112
View Solution24 women can complete a work in 45 days. If 18 women are employed, then in how many days the work would be completed?
View Solution24 women can complete a work in 45 days. If 18 women are employed, then in how many days the work would be completed?
View Solution15 men would finish a piece of work in 210 days. But at the end of every 10 days. 15 additional men are employed. In how many days will it be finished ?
View SolutionA contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
View Solution