A can do a work in 8 hours & B can do the same work in 12 hours. If they workalternatively (one hour A works and one hour B works) and A starts the work at 9 AM, then the work will be completed at __O'clock.
7:00 PM
5:30 PM
6:30 AM
6:30 PM
The correct Answer is:D
To solve the problem step by step, we will first determine the work done by A and B in one hour and then calculate how long it will take them to complete the work when they work alternatively.
Step 1: Determine the work done by A and B in one hour.
- A can complete the work in 8 hours, so A's work rate is:
Work rate of A=18 of the work per hour
- B can complete the work in 12 hours, so B's work rate is:
Work rate of B=112 of the work per hour
Step 2: Find the combined work done in 2 hours (1 hour by A and 1 hour by B).
- In the first hour, A works:
Work done by A in 1 hour=18
- In the second hour, B works:
Work done by B in 1 hour=112
- Therefore, the total work done in 2 hours is:
Total work in 2 hours=18+112
- To add these fractions, we need a common denominator. The least common multiple of 8 and 12 is 24.
18=324,112=224
- So,
Total work in 2 hours=324+224=524
Step 3: Calculate how many 2-hour cycles are needed to complete the work.
- The total work to be done is 1 (the whole work).
- In 2 hours, they complete 524 of the work.
- To find out how many such cycles are needed to complete 1 unit of work:
Number of cycles=1524=245=4.8 cycles
Step 4: Calculate the total time taken to complete the work.
- Each cycle takes 2 hours, so:
Time for 4 complete cycles=4×2=8 hours
- After 4 cycles (8 hours), they will have completed:
4×524=2024=56 of the work
- Remaining work:
1−56=16
Step 5: Determine who will work next and how long it will take to finish the remaining work.
- A will work next (since they alternate and A started first).
- A's work rate is 18 of the work per hour.
- To complete 16 of the work:
Time taken by A=1618=86=43 hours≈1 hour and 20 minutes
Step 6: Calculate the total time from the start.
- Total time taken = 8 hours (for 4 cycles) + 1 hour and 20 minutes = 9 hours and 20 minutes.
- If they started at 9 AM, we add 9 hours and 20 minutes:
9 AM+9 hours+20 minutes=6:20 PM
Final Answer:
The work will be completed at 6:20 PM.
---
- A can complete the work in 8 hours, so A's work rate is:
Work rate of A=18 of the work per hour
- B can complete the work in 12 hours, so B's work rate is:
Work rate of B=112 of the work per hour
- In the first hour, A works:
Work done by A in 1 hour=18
- In the second hour, B works:
Work done by B in 1 hour=112
- Therefore, the total work done in 2 hours is:
Total work in 2 hours=18+112
- To add these fractions, we need a common denominator. The least common multiple of 8 and 12 is 24.
18=324,112=224
- So,
Total work in 2 hours=324+224=524
- The total work to be done is 1 (the whole work).
- In 2 hours, they complete 524 of the work.
- To find out how many such cycles are needed to complete 1 unit of work:
Number of cycles=1524=245=4.8 cycles
- Each cycle takes 2 hours, so:
Time for 4 complete cycles=4×2=8 hours
- After 4 cycles (8 hours), they will have completed:
4×524=2024=56 of the work
- Remaining work:
1−56=16
- A will work next (since they alternate and A started first).
- A's work rate is 18 of the work per hour.
- To complete 16 of the work:
Time taken by A=1618=86=43 hours≈1 hour and 20 minutes
- Total time taken = 8 hours (for 4 cycles) + 1 hour and 20 minutes = 9 hours and 20 minutes.
- If they started at 9 AM, we add 9 hours and 20 minutes:
9 AM+9 hours+20 minutes=6:20 PM
The work will be completed at 6:20 PM.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 4 hours. (B + C) can do the same work in 3 hours. (A + C) can do the same work in 2 hours. In how many hours will B do this work alone ?
View SolutionIf a man cando a piece of work in 8 hours and a women can do the same work in 12 hours, then find the time it takes for 2 men and 3 women to finish the same work.
View Solution
Knowledge Check
A can do a work in 8 hours & B can do the same work in 12 hours. If they workalternatively (one hour A works and one hour B works) and A starts the work at 9 AM, then the work will be completed at __O'clock.
A10:30P.MB7:30PMC8:30P.MD6:30P.MA can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :
A1 hourB2 hoursC3 hoursD4 hoursA can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
A5511B4511C6411D6511
If a man cando a piece of work in 8 hours and a women can do the same work in 12 hours, then find the time it takes for 2 men and 3 women to finish the same work.
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionAnuradha can do a piece of work in 6 hours. What part of the work can she do in 1 hour, in 5 hours, in 6 hours?
View SolutionA can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :
View SolutionA can do a piece of work in 8 hours while B aline can do it in 12 hours. Both A and B working together can finish the work in time ?
View Solution