A can do a work in 8 hours & B can do the same work in 12 hours. If they workalternatively (one hour A works and one hour B works) and A starts the work at 9 AM, then the work will be completed at __O'clock.

A

7:00 PM

B

5:30 PM

C

6:30 AM

D

6:30 PM

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work done by A and B in one hour and then calculate how long it will take them to complete the work when they work alternatively.

Step 1: Determine the work done by A and B in one hour.
- A can complete the work in 8 hours, so A's work rate is:
Work rate of A=18 of the work per hour
- B can complete the work in 12 hours, so B's work rate is:
Work rate of B=112 of the work per hour

Step 2: Find the combined work done in 2 hours (1 hour by A and 1 hour by B).
- In the first hour, A works:
Work done by A in 1 hour=18
- In the second hour, B works:
Work done by B in 1 hour=112
- Therefore, the total work done in 2 hours is:
Total work in 2 hours=18+112
- To add these fractions, we need a common denominator. The least common multiple of 8 and 12 is 24.
18=324,112=224
- So,
Total work in 2 hours=324+224=524

Step 3: Calculate how many 2-hour cycles are needed to complete the work.
- The total work to be done is 1 (the whole work).
- In 2 hours, they complete 524 of the work.
- To find out how many such cycles are needed to complete 1 unit of work:
Number of cycles=1524=245=4.8 cycles

Step 4: Calculate the total time taken to complete the work.
- Each cycle takes 2 hours, so:
Time for 4 complete cycles=4×2=8 hours
- After 4 cycles (8 hours), they will have completed:
4×524=2024=56 of the work
- Remaining work:
156=16

Step 5: Determine who will work next and how long it will take to finish the remaining work.
- A will work next (since they alternate and A started first).
- A's work rate is 18 of the work per hour.
- To complete 16 of the work:
Time taken by A=1618=86=43 hours1 hour and 20 minutes

Step 6: Calculate the total time from the start.
- Total time taken = 8 hours (for 4 cycles) + 1 hour and 20 minutes = 9 hours and 20 minutes.
- If they started at 9 AM, we add 9 hours and 20 minutes:
9 AM+9 hours+20 minutes=6:20 PM

Final Answer:
The work will be completed at 6:20 PM.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a work in 8 hours & B can do the same work in 12 hours. If they workalternatively (one hour A works and one hour B works) and A starts the work at 9 AM, then the work will be completed at __O'clock.

    A10:30P.M
    B7:30PM
    C8:30P.M
    D6:30P.M
  • A can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :

    A1 hour
    B2 hours
    C3 hours
    D4 hours
  • A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.

    A5511
    B4511
    C6411
    D6511